Revision History
C |
Updated Table 4.1, Section 6.2.1, 6.4.1, 7.2.1 and Appendix K |
6 June 2019 |
B |
Revised the effective date of CNP (Table 1.3) and correct turbidity resolution (Table 2.8, Appendix D) |
5 October 2018 |
A |
First Submission |
14 August 2018 |
Rev. |
Description of Modification |
Date |
Content
2. Marine Water Quality Monitoring
8. Summary of Monitoring Exceedance, Complaints, Notification of Summons and Prosecutions
11. Conclusion and Recommendations
Appendix A |
|
Appendix B |
Summary of Implementation Status of Environmental Mitigation |
Appendix C |
|
Appendix D |
|
Appendix E |
|
Appendix F |
|
Appendix G |
|
Appendix H |
|
Appendix I |
|
Appendix J |
|
Appendix K |
|
Appendix L |
|
Appendix M |
|
Appendix N |
|
Appendix O |
|
Appendix P |
Executive Summary
Introduction
A1. The Project, Integrated Waste Management Facility (IWMF), is a Designated Project under the Environmental Impact Assessment Ordinance (Cap. 499) (EIAO) and is currently governed by a Further Environmental Permit (FEP No. FEP-01/429/2012/A) for the construction and operation of the Project.
A2. In accordance with the Updated Environmental Monitoring and Audit (EM&A) Manual for the Project, EM&A works for marine water quality, noise, waste management and ecology should be carried out by Environmental Team (ET), Acuity Sustainability Consulting Limited (ASCL), during the construction phase of the Project.
A3. This is the 1st Monthly EM&A Report, prepared by ASCL, for the Project summarizing the monitoring results and audit findings of the EM&A programme at and around Shek Kwu Chau (SKC) during the reporting period from 28 June 2018 to 31 July 2018.
Summary of Main Works Undertaken & Key Mitigation Measures Implemented
A4. Key activities carried out in this reporting period for the Project included the following:
· Marine Site Investigation Works
· Laying Geotextile and Sand Blanket for DCM (Deep Cement Mixing) Trial
· DCM Site Trial
A5. The major environmental impacts brought by the above construction activities include:
· Water quality impact from laying of Sand Blanket and injection of DCM
· Disturbance and possible trapping of Finless Porpoise by silt curtains
A6. The key environmental mitigation measures implemented for the Project in this reporting period associated with the construction activities include:
· Reduction of noise from equipment and machinery on-site;
· Installation of silt curtains for the sand blanket laying works and DCM trial;
· Sorting and storage of general refuse and construction waste;
· Management of chemicals and avoidance of oil spillage on-site; and
· Implementation of MMEZ (Marine Mammal Exclusion Zone) and inspection of enclosed environment within silt curtains as per DMPFP (Detailed Monitoring Programme of Finless Porpoise)
Summary of Exceedance & Investigation & Follow-up
A7. The EM&A works for construction noise, water quality, construction waste, coral, marine mammal and White-Bellied Sea Eagle (WBSE) were conducted during the reporting period in accordance with the Updated EM&A Manual.
A8. No exceedance of the Action or Limit Levels in relation to the construction noise, construction waste, coral and WBSE monitoring was recorded in the reporting month.
A9. Thirteen of the water quality monitoring results for Suspended Solid (SS) obtained during the reporting period had exceeded the relevant Action or Limit Levels, where findings from investigations carried out immediately for each of the exceedance cases had showed that these exceedances were unrelated to the Project.
A10. No project-related Action Level & Limit Level exceedance was recorded during the reporting period.
A11. Weekly site inspections of the construction works by ET were carried out on 3, 10, 20 and 24 July 2018 to audit the mitigation measures implementation status. Monthly joint site inspection was carried out on 20 July 2018 by ET and IEC. Observations have been recorded in the site inspection checklists and provided to the contractors together with the appropriate follow- up actions where necessary.
Complaint Handling and Prosecution
A12. No project-related environmental complaint was received during the reporting period.
A13. Neither notifications of summons nor prosecution was received for the Project.
Reporting Change
A14. There were no changes to be reported that may affect the on-going EM&A programme.
Summary of Upcoming Key Issues and Key Mitigation Measures
A15. Key activities anticipated in the next reporting period for the Project will include the following:
· Marine Site Investigation Works
· Laying Geotextile and Sand Blanket for Static Loading Test
· Static Loading Test
A16. The major environmental impacts brought by the above construction activities will include:
· Water quality impact from laying of Sand Blanket
· Disturbance and possible trapping of Finless Porpoise by silt curtains
A17. The key environmental mitigation measures for the Project in the coming reporting period associated with the construction activities will include:
· Reduction of noise from equipment and machinery on-site;
· Installation of silt curtains for the sand blanket laying works;
· Sorting and storage of general refuse and construction waste;
· Management of chemicals and avoidance of oil spillage on-site; and
· Implementation of MMEZ and inspection of enclosed environment within silt curtains as per DMPFP
1. Basic Project Information 1.1 Background 1.1.1 The Government of Hong Kong SAR will develop the Integrated Waste Management Facilities (IWMF) Phase 1 (hereafter the Project) with incineration to achieve substantial bulk reduction of unavoidable municipal solid waste (MSW) and to recover energy from the incineration process. The IWMF will be on an artificial island to be formed by reclamation at the south-western coast of Shek Kwu Chau. Keppel Seghers Zhen Hua Joint Venture (KSZHJV) was awarded the contract under Contract No. EP/SP/66/12 Integrated Waste Management Facilities Phase 1 to construct and operate the Project. 1.1.2 An environmental impact assessment (EIA) study for the Project have been conducted and the EIA Report was approved under the Environmental Impact Assessment Ordinance on 17 January 2012. An Environmental Permit (EP) (EP No.: EP-429/2012) was granted to EPD on 19 January 2012 for the construction and operation of the Project. Subsequently, the EP was amended (EP No.: EP-429/2012/A) and a further EP (FEP) (EP No.: FEP-01/429/2012/A) was granted to the Keppel Seghers Zhen Hua Joint Venture (KSZHJV) on 27 December 2017. 1.1.3 The key design and construction elements of the Project include the Design and the Works including but not limited to the design, engineering procurement, construction, testing and commissioning of the Facility including:
· Ground Treatment works;
· Seawall and Breakwater construction;
· Non-dredged Reclamation;
· Other Marine works and Harbour and Port Facilities,
· Site formation,
· Municipal Solid Waste (MSW) Treatment Processes,
· Energy Recovery for Power Generation and Surplus Electricity export,
· Wastewater treatment process,
· Desalination and water treatment process,
· Civil works;
· Building and Structural works,
· Electrical and Mechanical works,
· Building Services,
· Architectural and Landscaping works, and
· All other design and works required for the operation and maintenance of the Facility
· according to the Contract requirements
1.1.4 The location of the IWMF near Shek Kwu Chau (SKC) and general layout of IWMF are shown in Figure 1.1 and Figure 1.2 respectively.
|
Figure 1.1 Location of the IWMF at the Artificial Island near SKC |
|
Figure 1.2 General Layout of the IWMF at the Artificial Island near SKC |
Figure 1.3 Project Organization Chart |
Table 1.1 Contact Details of Key Personnel
Party |
Position |
Name |
Telephone no. |
Keppel Seghers Zhen Hua Joint Venture |
Project Manager |
Peter Chung |
2192-0606 |
Acuity Sustainability Consulting Limited |
Environmental Team Leader |
Robin Ho |
2698-6833 |
ERM-Hong Kong, Limited |
Independent Environmental Checker |
Jovy Tam (until 31st July 2018) Mandy To |
2271-3000 |
Table 1.2 Summary of the Construction Activities Undertaken during the Reporting Month
Location of works |
Construction activities undertaken |
Remarks on progress |
Seawall and breakwater locations |
· Marine site investigation works |
· 19 out of 51 drill holes were completed |
Location of DCM Site Trial |
· DCM site trial · Laying of geotextile · Laying of sand blanket |
· On-going |
Table 1.3 Summary of the Status of Valid Environmental Licence, Notification, Permit and Documentations
Permit/ Licences/ Notification |
Reference |
Validity Period |
Remarks |
Variation of Environmental Permit |
EP-429/2012/A |
Throughout the Contract |
|
Further Environmental Permit |
FEP-01/429/2012/A |
Throughout the Contract |
|
Notification of Construction Works under the Air Pollution Control (Construction Dust) Regulation (Form NA) |
Ref No.: 428778 |
15/12/2017-22/09/2024 |
|
Wastewater Discharge Licence |
- |
- |
Under Application |
Chemical Waste Producer Registration |
WPN0017-933-K3301 |
Throughout the Contract |
|
Construction Noise Permit |
GW-RS0534-18 |
22/6/2018-20/12/2018 |
|
Billing Account for Disposal of Construction Waste |
A/C No.:7029768 |
Throughout the Contract |
|
Table 1.4 Summary of Status for Key Environmental Aspects under the Updated EM&A Manual
1.5.3 Other than the EM&A works by ET, environmental briefings, trainings and regular environmental management meetings were conducted, in order to enhance environmental awareness and closely monitor the environmental performance of the contractors. 1.5.4 The EM&A programme has been implemented in accordance with the recommendations presented in the approved EIA Report and the Updated EM&A Manual. A summary of implementation status of the environmental mitigation measures for the construction phase of the Project during the reporting period is provided in Appendix B.
2. Marine Water Quality Monitoring 2.1 Water Quality Requirements 2.1.1 To ensure no adverse water quality impact, water quality monitoring is recommended to be carried out at the nearby water sensitive receivers (WSRs) during construction phase including proposed reclamation, breakwater construction, etc. The construction works for IWMF and DCM trial works were commenced on 28 June 2018 and 22 July 2018 respectively. 2.1.2 In accordance with the Updated EM&A Manual, impact water quality monitoring were conducted 3 days per week at mid-flood and mid-tide to obtain impact water quality levels at the eleven monitoring stations during general water quality monitoring and fourteen monitoring stations during regular DCM monitoring for the construction period. 2.2 Water Quality Paramters, Time, Frequency 2.2.1 Dissolved Oxygen (DO), Turbidity, Suspended Solids (SS), Salinity and pH have been undertaken at the eleven monitoring stations during general water quality monitoring. Beside the above parameters, monitoring for Total Alkalinity, Current Velocity and Current Direction have been undertaken at all fourteen monitoring stations (including S1, S2 and S3) during regular DCM monitoring. While the same parameters monitored during regular DCM monitoring have been undertaken at twelve immediate upstream and downstream area to the DCM works location during intensive DCM monitoring. 2.2.2 Current velocity and direction, DO, temperature, salinity, turbidity and pH were measured in-situ and the SS, Total Alkalinity were assayed in a HOKLAS laboratory. 2.2.3 In associate with the water quality parameters, other relevant data were also measured, such as monitoring location/position, time, water depth, sampling depth, tidal stages, weather conditions and any special phenomena or work underway nearby were also recorded. The monitoring schedule is provided in Appendix C. 2.2.4 Impact water quality monitoring was conducted 3 days per week in the reporting period. All parameters were monitored during mid-flood and mid-ebb tides at three water depths for general water quality monitoring and regular DCM monitoring. The interval between two sets of monitoring has not been less than 36 hours. 2.2.5 Table 2.1 summarizes the monitoring parameters, frequency and duration of the impact water quality monitoring.
Table 2.1 Water Quality Monitoring Parameters, Frequency and Duration
Parameter, unit |
Frequency |
No. of Depths |
· Water Depth(m) · Temperature(oC) · Salinity(ppt) · pH (pH unit) · Dissolved Oxygen (DO)(mg/L and % of saturation) · Turbidity(NTU) · Suspended Solids (SS), mg/L · Total alkalinity · Current velocity · Direction |
Impact monitoring: 3 days per week, at mid-flood and mid-ebb tides
|
3 water depths: 1m below sea surface, mid-depth and 1m above sea bed. If the water depth is less than 3m, mid-depth sampling only. If water depth less than 6m, mid-depth may be omitted.
|
|
Figure 2.1 Water monitoring locations at Artificial Island near SKC |
Table 2.2 - Locations of Marine Water Quality Stations
Monitoring station |
Description |
Easting |
Northing |
B1 |
Beach - Cheung Sha Lower |
813342 |
810316 |
B2 |
Beach - Pui O |
815340 |
811025 |
B3 |
Beach - Yi Long Wan |
817210 |
808395 |
B4 |
Beach - Tai Long Wan |
817784 |
808682 |
H1 |
Horseshoe Crab - Shek Kwu Chau |
816477 |
806953 |
C1 |
Control Station |
810850 |
806288 |
C2 |
Control Station |
819421 |
808053 |
F1 |
Cheung Sha Wan Fish Culture Zone |
818631 |
810966 |
S1 |
Submarine Cable Landing Site |
814245 |
810335 |
S2 |
Submarine Cable |
815076 |
807747 |
S3 |
Submarine Cable Landing Site |
816420 |
805621 |
CR1 |
Coral |
817144 |
805597 |
CR2 |
Coral |
816512 |
805882 |
M1 |
Tung Wan |
821572 |
807799 |
· Two monitoring stations upstream and at 150 m envelope of DCM group works area (Representative Control stations).
· Five monitoring stations downstream and at 150 m envelope of DCM group works area (Impact 1 stations).
· Five monitoring stations downstream and at 250 m envelope of DCM group works area (Impact 2 stations).
· Monitoring stations should be at least 50 m apart;
· Downstream monitoring stations should be perpendicular to the tidal direction.
|
Figure 2.2 Water monitoring locations during intensive DCM monitoring |
In-situ Measurement
2.4.4 Levels of DO, pH, temperature, turbidity and salinity were measured in-situ by portable and weatherproof measuring instrument, YSI ProDSS and Horiba U-53 Multiparameter complete with cable and sensor. (Refer to http://www.ysi.com/ProDSS for YSI ProDSS technical specification and http://www.horiba.com/process-environmental/products/water-treatment-environment/details/u-50-multiparameter-water-quality-checker-368/ for Horiba U-53 technical specification ). Water current velocity and Water Current direction were measured by by SonTek Hydrosurveyor (Refer to https://www.sontek.com/media/pdfs/riversurveyor-s5-m9-brochure.pdf for SonTek Hydrosurveyor M9 technical specification). Parameters measured by in-situ measurement is tabulated in Table 2.3Table 2.3 - Parameters Measured by In-situ Measurement
Parameter |
Resolution |
Range |
Temperature |
0.1 oC |
-5-70 oC |
Dissolved Oxygen (DO) |
0.01 mg/L |
0-50.0 mg/L |
Turbidity |
0.1 NTU |
0-1000 NTU |
pH |
0.01 pH |
pH 0-14 |
Salinity |
0.01 ppt |
0-40 ppt |
Water Current Velocity |
0.001m/s |
±20m/s |
Water Current Direction |
±1o |
±2o |
Laboratory Analysis
2.4.5 Analysis of Total Alkalinity and SS should be carried out in a HOKLAS accredited laboratory, as shown in Appendix E. Sufficient water samples were collected at the monitoring stations for carrying out the laboratory determinations. The determination work was started within 24 hours after collection of the water samples. Analytical methods and detection limits for SS are present in Table 2.4.
Table 2.4 - Analytical Methods Applied to Water Quality Samples
Parameter |
Analytical method |
Detection Level |
Suspended Solids, SS |
APHA 2540 Di |
1 mg/L |
Total Alkalinity |
APHA 2320 |
0.01 mg/L |
i. "APHA 2540 D" stands for American Public Health Association Standard Methods for the Examination of Water and Wastewater, 23rd Edition.
Field Log
2.4.6 Other relevant data was recorded, such as: monitoring location / position, time, water depth, weather conditions and any special phenomena underway near the monitoring station. 2.5 Monitoring Equipment 2.5.1 Equipment used in the impact water quality monitoring programme is summarized in Table 2.5 below. Calibration certificates for the water quality monitoring equipment are attached in Appendix F.Table 2.5 Impact Water Quality Monitoring Equipment
Monitored Parameter |
Equipment |
Brand and Model |
DO, Temperature, Salinity, pH and Turbidity |
Multi-functional Meter |
YSI ProDSS |
Coordinates |
Positioning Equipment |
Garmin GPSMAP 78s |
Water depth |
Water Depth Detector |
Hummingbird 160 Portable |
SS, Alkalinity Level |
Water Sampler |
Wildco 2 L Water Sampler with messenger |
Water Current Velocity |
Current Meter |
Valeport Model 106 |
Water Current Direction |
Current Meter |
Valeport Model 106 |
2.5.2 Current Meter
A portable, electronic current meter having equivalent functions and performance as Valeport 108 MKIII current meter was used for measuring current velocity and direction.
2.5.3 Dissolved Oxygen and Temperature Measuring Equipment
The instrument was a portable and weatherproof DO probe mounted on the multi-functional meter complete with cable and sensor, and use a DC power source. The equipment was capable of measuring:
l A DO level in the range of 0 ‑ 50 mg/L; and
l Temperature of -5 ‑ 70 degree Celsius.
2.5.4 Turbidity Measurement Instrument
The instrument was a portable and weatherproof turbidity-measuring probe mounted on the multi-functional meter using a DC power source. It had a photoelectric sensor capable of measuring turbidity between 0 - 1000 NTU.
2.5.5 pH Measurement Instrument
The probe was consisted of a potentiometer, a glass electrode, a reference electrode and a temperature-compensating device mounted on the multi-functional meter. It was readable to 0.1 pH in a range of 0 to 14. Standard buffer solutions of at least pH 7 and pH 10 were used for calibration of the instrument before and after use.
2.5.6 Salinity Measurement Instrument
A portable salinometer mounted on the multi-functional meter capable of measuring salinity in the range of 0-40 parts per thousand (ppt) was provided for measuring salinity of the water at each monitoring location.
2.5.7 Sampler
The water sampler comprised a transparent PVC cylinder, with a capacity of not less than 2 litres, which can be effectively sealed with latex cups at both ends. The sampler have a positive latching system to keep it open and prevent premature closure until released by a messenger when the sampler is at the selected water depth.
2.5.8 Sample Containers and Storage
Water samples for SS were stored in high density polythene bottles with no preservative added, packed in ice (cooled to 4°C without being frozen) and delivered to the laboratory and analysed as soon as possible after collection. Sufficient volume of samples was collected to achieve the detection limit stated in Table 2.4.
2.5.9 Water Depth Detector
A portable, battery-operated echo sounder was used for the determination of water depth at each designated monitoring station. This unit could either be hand held or affixed to the bottom of the work boat, if the same vessel is to be used throughout the monitoring programme.
2.5.10 Monitoring Position Equipment
Hand-held digital Differential Global Positioning System (DGPS) with way point bearing indication and Radio Technical Commission for maritime (RTCM) Type 16 error message screen pop-up facilities (for real-time auto-display of error messages and DGPS corrections from the Hong Kong Hydrographic Office) was provided and used to ensure that the water sampling locations were correct during the water quality monitoring work.
2.6 Maintenance and Calibration 2.6.1 The multi-functional meters were checked and calibrated before use. Multi-functional meters were certified by a laboratory accredited under HOKLAS or any other international accreditation scheme, and subsequently re-calibrated at three monthly intervals throughout all stages of the water quality monitoring. Responses of sensors and electrodes were checked with certified standard solutions before each use. Wet bulb calibration for a DO meter was carried out before commencement of monitoring and after completion of all measurements each day. Calibration was not conducted at each monitoring location as daily calibration is adequate for the type of DO meter employed. 2.6.2 Sufficient stocks of spare parts were provided and maintained for replacements when necessary. Backup monitoring equipment was prepared for uninterrupted monitoring during equipment maintenance or calibration during monitoring. 2.7 Action and Limit Levels 2.7.1 The Action and Limit Levels have been set based on the derivation criteria specified in the Updated EM&A Manual and Detailed DCM Plan, as shown in Table 2.6 below.Table 2.6 Criteria of Action and Limit Levels for Water Quality
Parameters |
Action |
Limit |
Construction Phase Impact Monitoring |
||
DO in mg/L |
≤ 5 %-ile of baseline data |
≤ 4 |
SS in mg/L |
≥ 95 %-ile of baseline data or 120% of control stations SS at the same tide of the same day of measurement, whichever is higher |
≥ 99 %-ile of baseline data or 130% of control station's SS at the same tide of the same day of measurement, whichever is higher |
Turbidity in NTU |
≥ 95 %-ile of baseline data or 120% of control stations turbidity at the same tide of the same day of measurement, whichever is higher |
≥ 99 %-ile of baseline data or 130% of control station's turbidity at the same tide of the same day of measurement, whichever is higher |
Temperature in°C |
1.8°C above the temperature recorded at representative control station at the same tide of the same day |
2°C above the temperature recorded at representative control station at the same tide of the same day |
Total Alkalinity in mg/L |
≥ 95 %-ile of baseline data or 120% of representative control station at the same tide of the same day, whichever is higher |
≥ 99 %-ile of baseline data or 130% of representative control station at the same tide of the same day, whichever is higher |
Table 2.7 Derived Action and Limit Levels for Water Quality Monitoring
Parameters |
Action |
Limit |
Construction Phase Impact Monitoring |
||
DO in mg/L |
≤ 7.13 |
≤ 4 |
SS in mg/L |
≥ 8 or 120% of control stations SS at the same tide of the same day of measurement, whichever is higher |
≥ 10 or 130% of control station's SS at the same tide of the same day of measurement, whichever is higher |
Turbidity in NTU |
≥ 5.6 or 120% of control stations turbidity at the same tide of the same day of measurement, whichever is higher |
≥ 12.81 or 130% of control station's turbidity at the same tide of the same day of measurement, whichever is higher |
Temperature in°C |
1.8°C above the temperature recorded at representative control station at the same tide of the same day |
2°C above the temperature recorded at representative control station at the same tide of the same day |
Total Alkalinity in mg/L |
≥116 or 120% of control stations Total Alkalinity at the same tide of the same day of measurement, whichever is higher |
≥ 118 or 130% of control stations Total Alkalinity at the same tide of the same day of measurement, whichever is higher |
Notes:
i. "Depth-averaged" is calculated by taking the arithmetic means of reading of all three depths.
ii. For DO, non-compliance of the water quality limits occurs when monitoring result is lower than the limits.
iii. For turbidity, SS and Salinity, non-compliance of the water quality limits occurs when monitoring result is higher than the limits.
2.7.3 If exceedances were found during water quality monitoring, the actions in accordance with the Event and Action Plan shall be carried out according to Appendix G. 2.8 Monitoring Results and Observations 2.8.1 DCM injection works for DCM Site Trial was commenced on 22 July 2018 and completed on 28 July 2018. During the reporting period, general water quality monitoring was conducted on 29 June, 3, 5, 7, 10, 12, 14, 16, 18, 20 and 30 July 2018 at all the eleven monitoring stations. General DCM monitoring including monitoring station S1, S2 and S3 were conducted on 23, 25 and 27 July 2018. Monitoring results of 7 key parameters: Salinity, DO, turbidity, SS, pH, temperature and total alkalinity in this reporting month, are summarized in Table 2.8, and details results are presented in Appendix D.
Table 2.8 Summary of Impact Water Quality Monitoring Results
Locations |
Parameters |
||||||||
Salinity (ppt) |
Dissolved Oxygen (mg/L) |
pH |
Turbidity (NTU) |
Suspended Solids (mg/L) |
Temp. (oC) |
Total Alkalinity (mg/L) note ii |
|||
Surface & Middle |
Bottom |
||||||||
B1 |
Avg. |
26.45 |
7.93 |
7.85 |
8.26 |
2.0 |
7 |
28.5 |
107.2 |
Min. |
22.55 |
4.38 |
3.23 |
7.89 |
0.9 |
2 |
26.6 |
104.0 |
|
Max. |
27.87 |
11.61 |
11.59 |
8.51 |
3.1 |
18 |
30.8 |
110.0 |
|
B2 |
Avg. |
26.52 |
7.72 |
7.62 |
8.25 |
2.0 |
6 |
28.5 |
107.1 |
Min. |
22.99 |
2.99 |
2.65 |
7.90 |
0.8 |
3 |
26.6 |
104.0 |
|
Max. |
27.83 |
11.60 |
11.60 |
8.51 |
5.7 |
10 |
31.0 |
109.0 |
|
B3 |
Avg. |
26.57 |
7.67 |
7.72 |
8.24 |
2.1 |
6 |
28.3 |
107.1 |
Min. |
22.72 |
4.53 |
4.44 |
7.88 |
1.0 |
3 |
26.6 |
104.0 |
|
Max. |
29.84 |
11.64 |
11.62 |
8.50 |
14.6 |
12 |
30.9 |
109.0 |
|
B4 |
Avg. |
26.41 |
8.01 |
8.01 |
8.27 |
1.9 |
7 |
28.5 |
107.8 |
Min. |
22.87 |
4.45 |
3.35 |
7.91 |
0.9 |
2 |
26.6 |
105.0 |
|
Max. |
27.93 |
11.69 |
11.66 |
8.51 |
3.1 |
18 |
31.0 |
111.0 |
|
C1 |
Avg. |
26.62 |
7.85 |
7.74 |
8.25 |
2.0 |
7 |
28.5 |
107.8 |
Min. |
22.84 |
2.77 |
2.56 |
7.88 |
0.9 |
2 |
26.6 |
105.0 |
|
Max. |
28.75 |
11.54 |
11.51 |
8.53 |
9.9 |
17 |
30.9 |
110.0 |
|
C2 |
Avg. |
26.71 |
7.81 |
7.55 |
8.24 |
1.9 |
7 |
28.4 |
107.6 |
Min. |
22.74 |
2.52 |
2.41 |
7.84 |
0.7 |
2 |
26.5 |
104.0 |
|
Max. |
28.45 |
11.71 |
11.71 |
8.52 |
3.6 |
16 |
31.1 |
110.0 |
|
CR1 |
Avg. |
26.60 |
7.90 |
7.78 |
8.26 |
1.9 |
7 |
28.5 |
107.3 |
Min. |
22.69 |
3.33 |
2.31 |
7.96 |
0.8 |
3 |
26.6 |
105.0 |
|
Max. |
30.54 |
11.64 |
11.66 |
8.50 |
4.0 |
17 |
30.9 |
110.0 |
|
CR2 |
Avg. |
26.56 |
7.94 |
7.78 |
8.26 |
1.9 |
6 |
28.5 |
107.5 |
Min. |
23.07 |
3.66 |
2.88 |
7.89 |
0.8 |
2 |
26.6 |
105.0 |
|
Max. |
30.85 |
11.61 |
11.62 |
8.52 |
3.2 |
13 |
30.9 |
110.0 |
|
F1 |
Avg. |
26.72 |
7.78 |
7.56 |
8.25 |
1.9 |
7 |
28.4 |
107.6 |
Min. |
22.73 |
2.84 |
2.69 |
7.85 |
0.8 |
2 |
26.2 |
105.0 |
|
Max. |
29.34 |
11.75 |
11.73 |
8.52 |
4.3 |
18 |
30.8 |
110.0 |
|
H1 |
Avg. |
26.63 |
7.82 |
7.65 |
8.26 |
2.0 |
7 |
28.5 |
107.8 |
Min. |
23.07 |
2.81 |
2.80 |
7.88 |
0.8 |
2 |
26.6 |
105.0 |
|
Max. |
28.53 |
11.64 |
11.62 |
8.52 |
4.7 |
18 |
31.0 |
110.0 |
|
M1 |
Avg. |
26.86 |
7.79 |
7.51 |
8.24 |
2.0 |
7 |
28.4 |
107.6 |
Min. |
22.73 |
1.98 |
1.72 |
7.82 |
0.8 |
2 |
26.6 |
106.0 |
|
Max. |
32.53 |
11.79 |
11.75 |
8.55 |
5.6 |
14 |
30.9 |
109.0 |
|
S1 |
Avg. |
27.47 |
10.30 |
10.31 |
8.46 |
1.4 |
7 |
29.6 |
107.5 |
Min. |
26.72 |
9.04 |
9.15 |
8.41 |
1.0 |
4 |
28.9 |
105.0 |
|
Max. |
27.86 |
11.59 |
11.59 |
8.53 |
1.9 |
12 |
30.9 |
110.0 |
|
S2 |
Avg. |
27.47 |
10.32 |
10.31 |
8.47 |
1.3 |
7 |
29.5 |
107.6 |
Min. |
26.72 |
9.12 |
9.02 |
8.43 |
0.8 |
3 |
28.8 |
105.0 |
|
Max. |
27.92 |
11.61 |
11.63 |
8.51 |
1.9 |
12 |
31.1 |
110.0 |
|
S3 |
Avg. |
27.46 |
10.29 |
10.29 |
8.46 |
1.4 |
7 |
29.5 |
107.5 |
Min. |
26.71 |
9.00 |
9.02 |
8.40 |
0.9 |
3 |
28.8 |
104.0 |
|
Max. |
27.92 |
11.62 |
11.59 |
8.51 |
1.9 |
11 |
30.8 |
110.0 |
Notes:
i. "Avg", Min and Max is the average, minimum and maximum respectively of the data from measurements conducted under mid-flood and mid-ebb tides at three water depths, except that of DO where the data for Surface & Middle and Bottom are calculated separately.
ii. Total alkalinity test only conducted on 23/07/2018, 25/07/2018 and 27/07/2018.
Table 3.1 Noise Monitoring Parameters, Time, Frequency and Duration
Monitoring Station |
Time |
Duration |
Parameters |
M1/ N_S1, M2/ N_S2, M3/ N_S3 |
Daytime: 0700-1900 hrs (during normal weekdays, not include Sunday or general holiday) |
Once per week Leq 5min/Leq 30min (average of 6 consecutive Leq 5min) |
Leq, L10 & L90 |
|
Figure 3.1 Noise monitoring locations at SKC |
Table 3.2 Noise Monitoring Location
Station |
NSR ID in EIA Report |
Noise Monitoring Location |
Type of sensitive receiver(s) |
Measurement Type |
M1 |
N_S1 |
Shek Kwu Chau Treatment & Rehabilitation Centre Hostel 1 |
Residential |
Façade |
M2 |
N_S2 |
Shek Kwu Chau Treatment & Rehabilitation Centre Hostel 2 |
Residential |
Façade |
M3 |
N_S3 |
Shek Kwu Chau Treatment & Rehabilitation Centre Hostel 3 |
Residential |
Façade |
l The microphone head of the lead level meter was normally positioned 1m exterior of the noise sensitive façade and lowered sufficiently so that the buildings external wall acts as a reflecting surface.
l The battery condition was checked to ensure good functioning of the meter.
l Parameters such as frequency weighting, the time weighting and the measurement time were set as follows:
- Frequency weight: A
- Time weighting: Fast
- Measurement time: 5 minutes
l Prior to and after noise measurement, the meter was calibrated using the calibrator for 94.0 dB at 1000Hz. If the difference in the calibration level before and after measurement is more than 1.0 dB, the measurement was considered invalid and repeat of noise measurement was required after re-calibration or repair of the equipment.
l Noise monitoring was carried out for 30 mins by sound level meter. At the end of the monitoring period, noise levels in term of Leq,L10,and L90 were recorded. In addition, site conditions and noise sources were recorded when the equipment were checked and inspected.
l All the monitoring data within the sound level meter system was downloaded through the computer software.
3.5 Monitoring Equipment 3.5.1 Integrated sound level meter was used for the noise monitoring. The meter shall be in compliance with the International Electrotechnical Commission Publications 651: 1979 (Type 1) and 804: 1985 (Type 1) specifications. 3.5.2 Equipment used in the impact noise monitoring programme is summarized in Table 3.3 below. Calibration certificates for the noise monitoring equipment are attached in Appendix H.Table 3.3 Impact Noise Monitoring Equipment
Equipment |
Brand and Model |
Sound Level Meter |
Nti XL2 |
Sound Level Meter Calibrator |
Rion NC-74 |
l The microphone head of the sound level meter and calibrator were cleaned with a soft cloth at quarterly intervals.
l The sound level meter and calibrator were checked and calibrated at yearly intervals
l Immediately prior to and following each noise measurement the accuracy of the sound level meter shall be checked using an acoustic calibrator generating a known sound pressure level at a known frequency. Measurements may be accepted as valid only if the calibration levels from before and after the noise measurement agree to within 1.0dB.
3.7 Action and Limit Levels 3.7.1 The Action/Limit Levels in line with the criteria of Practice Note for Professional Persons (ProPECC PN 2/93) Noise from Construction Activities Non-statutory Controls and Technical Memorandum on Environmental Impact Assessment Process issued by HKSAR Environmental Protection Department [EPD] under the Environmental Impact Assessment Ordinance, Cap 499, S.16 are presented in Table 3.4.Table 3.4 Action and Limit Levels for Noise
Time Period |
Action |
Limit (dB(A)) |
0700-1900 hrs on normal weekdays |
When one documented complaint is received |
75 dB(A) |
Table 3.5 Summary of Field Observation
Monitoring Station |
Major Noise Source |
M1 |
Nil |
M2 |
Nil |
M3 |
Newly installed air-conditioning units nearby |
3.8.4 No data from impact monitoring has exceeded the stipulated limit level at 75 dB(A).
Table 3.6 Summary of Impact Noise Monitoring Results
Location |
Noise in dB(A) |
||
Range of Leq 30min |
Range of L10 5min |
Range of L90 5min |
|
M1 |
47.7 57.8 |
49.5 64.1 |
39.5 45.4 |
M2 |
55.9 63.1 |
55.4 69.4 |
42.8 49.7 |
M3 |
51.3 59.8 |
50.9 66.6 |
39.9 45.9 |
4. Waste 4.1 The waste generated from this Project includes inert construction and demolition (C&D) materials, and non-inert C&D materials. Non-inert C&D materials are made up of general refuse, vegetative wastes and recyclable wastes such as plastics and paper/cardboard packaging waste. Steel materials generated from the project are also grouped into non-inert C&D materials as the materials were not disposed of with other inert C&D materials. 4.2 As advised by the Contractor, 0 m3 C&D material was generated on site in the reporting month. For C&D waste, 0 m3 of metals was generated and collected by registered recycling collector. 0 kg of paper cardboard packing were generated on site and collected by registered recycling collector. No plastic and chemical waste was collected by registered recycling collector and licensed chemical waste collectors respectively. 0 m3 of other types of wastes (e.g. general refuse) were generated on site and disposed of at Landfill. 4.3 With reference to relevant handling records and trip tickets of this Project, the quantities of different types of waste generated in the reporting month are summarised in Table 4.1. Details of cumulative waste management data are presented as a waste flow table in Appendix K.
Table 4.1 Quantities of Waste Generated from the Project
Reporting Month |
Actual Quantities of Inert C&D Materials Generated Monthly |
Actual Quantities of C&D Wastes Generated Monthly |
||||||||||||
Total Quantity Generated |
Hard Rock and Large Broken Concrete (see Note 1) |
Reused in the Contract |
Reused in other Projects |
Disposed as Public Fill |
Imported Fill |
Metals |
Paper / cardboard packaging |
Plastics (see Note 2) |
Chemical Waste |
Others, e.g. general refuse (see Note 3) |
||||
Sand |
Public Fill |
Rock |
||||||||||||
(in ,000m3) |
(in ,000m3) |
(in ,000m3) |
(in ,000m3) |
(in ,000m3) |
(in ,000m3) |
(in ,000kg) |
(in ,000kg) |
(in ,000kg) |
(in ,000kg) |
(in ,000L) |
(in ,000m3) |
|||
June & July 2019 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Notes:
1. Broken concrete for recycling into aggregates.
2. Plastic refer to plastic bottles / containers, plastic sheets / foam from packaging materials.
3. Use the conversion factor: 1 full load of dumping truck being equivalent to 6.5m3 by volume.
4.4 Although there is not much waste generation anticipated in the coming month from the Project, the Contractor is advised to sort and store any solid and liquid waste on-site properly prior to disposal.Table 5.1 Tagged Coral Monitoring Locations, Time and Frequency
Monitoring Location |
Monitoring Month/Year |
Frequency |
No. of Monitoring Survey |
10 selected hard coral colonies at control site / indirect impact site |
1st Month |
Weekly Survey |
4 |
2nd to 4th Months |
Monthly Survey |
3 |
|
5th to 76th Months |
Quarterly Survey |
24 |
|
Figure 5.1 Tagged Natural Corals at Indirect Impact Site Near SKC |
|
Figure 5.2 Tagged Natural Corals at Control Site Near Yuen Kong Chau |
Table 5.2 Tagged Natural Corals at Indirect Impact Site Near SKC
Coral # |
GPS Coordinates |
|
1 |
N22°0945.96 |
E113°5457.81 |
2 |
N22°0945.88 |
E113°5457.89 |
3 |
N22°0945.81 |
E113°5457.78 |
4 |
N22°0945.70 |
E113°5457.95 |
5 |
N22°0945.83 |
E113°5457.81 |
6 |
N22°0945.75 |
E113°5458.02 |
7 |
N22°0945.65 |
E113°5457.94 |
8 |
N22°0945.53 |
E113°5457.90 |
9 |
N22°0946.23 |
E113°5454.70 |
10 |
N22°0946.40 |
E113°5457.79 |
Table 5.3 Tagged Natural Corals at Control Site Near Yuen Kong Chau
Coral # |
GPS Coordinates |
|
11 |
N22°1129.12 |
E113°5908.98 |
12 |
N22°1129.08 |
E113°5909.06 |
13 |
N22°1129.01 |
E113°5909.21 |
14 |
N22°1129.01 |
E113°5909.29 |
15 |
N22°1129.00 |
E113°5909.37 |
16 |
N22°1129.00 |
E113°5909.50 |
17 |
N22°1128.94 |
E113°5909.48 |
18 |
N22°1128.99 |
E113°5909.36 |
19 |
N22°1128.95 |
E113°5909.29 |
20 |
N22°1129.00 |
E113°5909.18 |
· Gorgonian coral: Percentage of branches exhibiting partial mortality, secretion of mucus and degree of sedimentation;
· Hard coral: Percentage of surface area exhibiting partial mortality and blanched/bleached area of each coral colony and degree of sedimentation.Monitoring Equipment
5.5 Action and Limit Levels 5.5.1 Monitoring result was reviewed and compared against the below Action Level and Limit Level (AL/LL) as set with the below Table 5.4.
Table 5.4 Action and Limit Levels for Construction Phase Coral Monitoring
Parameter |
Action Level |
Limit Level |
Mortality |
If during Impact Monitoring a 15% increase in the percentage of partial mortality on the corals occurs at more than 20% of the tagged indirect impact site coral colonies that is not recorded on the tagged corals at the control site, then the Action Level is exceeded. |
If during Impact Monitoring a 25% increase in the percentage of partial mortality on the corals occurs at more than 20% of the tagged indirect impact site coral colonies that is not recorded on the tagged corals at the control site, then the Limit Level is exceeded. |
Table 5.5 Weather Condition for the First Month Construction Phase Monitoring
Date |
Condition |
Average Underwater Visibility |
5 July 2018 |
- Southwest force 5, - Sunny period |
Less than 0.5m |
12 July 2018 |
- Southwest force 4 to 5, - Sunny period |
Less than 0.5m |
21 July 2018 |
- South force 5 to 6, - Cloudy period |
Less than 0.5m |
26 July 2018 |
- Southwest force 3 to 4, - Sunny period |
Less than 0.5m |
Table 5.6 Sizes, Condition, Mortality, Bleaching and Sediment of 10 Natural Coral Colonies at Control Site during First Month Construction Phase Monitoring
Tag #
|
Species
|
Size (cm) Max. Diameter
|
Condition
|
Mortality (%) |
Bleaching (%) |
Sediment (%) |
||||||||||||
Baseline |
5-Jul |
12-Jul |
21-Jul |
26-Jul |
Baseline |
5-Jul |
12-Jul |
21-Jul |
26-Jul |
Baseline |
5-Jul |
12-Jul |
21-Jul |
26-Jul |
||||
1 |
Goniopora stutchburyi |
25 |
Good |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
2 |
Psammocora superficialis |
22 |
Good |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
3 |
Psammocora superficialis |
18 |
Good |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
4 |
Turbinaria peltata |
13 |
Good |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
5 |
Coscinaraea n sp. |
20 |
Good |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
6 |
Cyphastrea serailia |
43 |
Good |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
7 |
Psammocora superficialis |
16 |
Good |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
8 |
Goniopora stutchburyi |
21 |
Good |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
9 |
Goniopora stutchburyi |
11 |
Good |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
10 |
Psammocora superficialis |
18 |
Good |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Table 5.7 Sizes, Condition, Mortality, Bleaching and Sediment of 10 Natural Coral Colonies at Indirect Impact Site during First Month Construction Phase Monitoring
Tag #
|
Species
|
Size (cm) Max. Diameter
|
Condition
|
Mortality (%) |
Bleaching (%) |
Sediment (%) |
||||||||||||
Baseline |
5-Jul |
12-Jul |
21-Jul |
26-Jul |
Baseline |
5-Jul |
12-Jul |
21-Jul |
26-Jul |
Baseline |
5-Jul |
12-Jul |
21-Jul |
26-Jul |
||||
11 |
Psammocora superficialis |
25 |
Good |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
12 |
Psammocora superficialis |
35 |
Good |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
13 |
Psammocora superficialis |
21 |
Good |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
14 |
Goniopora stutchburyi |
13 |
Good |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
15 |
Psammocora superficialis |
23 |
Good |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
16 |
Goniopora stutchburyi |
14 |
Good |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
17 |
Psammocora superficialis |
7 |
Good |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
18 |
Psammocora superficialis |
12.5 |
Good |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
19 |
Psammocora superficialis |
10 |
Good |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
20 |
Psammocora superficialis |
8 |
Good |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
6. Marine Mammal 6.1 Monitoring Requirements 6.1.1 The marine mammal monitoring programme would focus on Finless Porpoise, as the study area near Shek Kwu Chau has been identified as a hotspot for this species, while the Chinese White Dolphins rarely occurred there in the past. 6.1.2 The monitoring would verify the predicted impacts on marine mammals, and examine whether the mitigation measures recommended in the EIA report have been effectively implemented to protect marine mammals from negative impacts from construction activities. 6.1.3 The Vessel-based Line-transect Survey, the Passive Acoustic Monitoring and the Land-based Theodolite Tracking will be conducted to provide systematic, quantitative measurements of occurrence, encounter rate, habitat use, movement and behavioral patterns of marine mammals within or near the Project Area during construction and operational phases. 6.1.4 The mammal monitoring works during construction consist of the following three survey methods:
· Vessel-based Line-transect Survey to monitor the occurrence of Finless Porpoises (and Chinese White Dolphins) in the study area during construction works, by comparing with the findings of the pre-construction marine mammal monitoring;
· Passive Acoustic Monitoring to study the usage of the Project Area and two control sites in South Lantau Waters by Finless Porpoise during construction works, in reference with the baseline findings of the pre-construction marine mammal monitoring; and
· Land-based Theodolite Tracking to study the movement and behavioural pattern of Finless Porpoise within and around the Project Area during construction works.
6.1.5 The marine mammal observation works of Marine Mammal Exclusion Zone (MMEZ) and Marine Mammal Watching as two of the specific mitigation measures recommended in the approved EIA report shall be fully and properly implemented for the Project to minimize disturbance on Finless Porpoise during construction and operational phases. 6.2 Survey Methods 6.2.1 Vessel-based Line-transect SurveyFor the vessel-based marine mammal surveys, the monitoring team adopted the standard line-transect method (Buckland et al. 2001) as same as that adopted during the EIA study and pre-construction phase monitoring to allow fair comparison of marine mammal monitoring results.
Eight transect lines are set at Southeast Lantau survey area, including Shek Kwu Chau, waters between Shek Kwu Chau and the Soko Islands, inshore waters of Lantau Island (e.g. Pui O Wan) as well as southwest corner of Cheung Chau as shown in Figure 6.1 below:
|
Figure 6.1 Line Transects for Marine Mammal Surveys |
The surveys should cover all 4 seasons in order to take natural fluctuation and seasonal variations into account for data analysis of distribution, encounter rate, density and habitat use of both porpoises and dolphins (if any). In comparison to the baseline monitoring results, results from the analyzed construction phase monitoring data would allow the detection of any changes of their usage of habitat, in response to the scheduled construction works. The monitoring surveys shall be conducted throughout the construction phase involving marine construction work with the frequency shown in Table 6.1 below:
Table 6.1 Vessel-based Line-transect Survey Frequency
Season |
Months |
Frequency |
Peak Season |
December, January, February, March, April & May |
Twice per month |
Non-peak Season |
June, July, August, September, October & November |
Once per month |
For each vessel survey, a 15-m inboard vessel with an open upper deck (about 4.5 m above water surface) would be used to make observations from the flying bridge area. Two experienced marine mammal observers (a data recorder and a primary observer) would make up the on-effort survey team, and the survey vessel would transit different transect lines at a constant speed of 13-15 km per hour. The data recorder shall search with unaided eyes and fill out the datasheets, while the primary observer shall search for dolphins and porpoises continuously through 7 x 50 marine binoculars. Both observers shall search the sea ahead of the vessel, between 270o and 90o (in relation to the bow, which is defined as 0o). Two additional experienced observers shall be available on the boat to work in shift (i.e. rotate every 30 minutes) in order to minimize fatigue of the survey team members. All observers shall be experienced in small cetacean survey techniques and identifying local cetacean species with extensive training by marine mammal specialist of the ET
During on-effort survey periods, the survey team shall record effort data including time, position (latitude and longitude), weather conditions (Beaufort sea state and visibility), and distance travelled in each series (a continuous period of search effort) with the assistance of a handheld GPS (Garmin eTrex Legend). Data including time, position and vessel speed would also be automatically and continuously logged by handheld GPS throughout the entire survey for subsequent review.
When porpoises or dolphins are sighted, the survey team shall end the survey effort, and immediately record the initial sighting distance and angle of the porpoise or dolphin group from the survey vessel, as well as the sighting time and position. Then the research vessel shall be diverted from its course to approach the animals for species identification, group size estimation, assessment of group composition, behavioural observations, and collection of identification photos (feasible only for Chinese White Dolphin). The perpendicular distance (PSD) of the porpoise or dolphin group to the transect line would then be calculated from the initial sighting distance and angle, which shall be used in the line-transect analysis for density and abundance estimation.
The line-transect survey data shall be integrated with a Geographic Information System (GIS) to visualize and interpret different spatial and temporal patterns of porpoise and dolphin distribution using their sighting positions collected from vessel surveys. Location data of porpoise and dolphin groups would be plotted on map layers of Hong Kong using a desktop GIS (e.g. ArcView© 3.1) to examine their distribution patterns in details. The encounter rate could be used as an indicator to determine areas or time periods of importance to porpoises within the study area. For encounter rate analysis of finless porpoises, only survey data collected under Beaufort 2 or below condition would be used for encounter rate analysis.
To take into account of the variations of survey effort across different sections within survey area, the quantitative grid analysis of habitat use would be conducted to examine finless porpoise usage among 1-km2 grids within the Southeast Lantau survey area. For the grid analysis, SPSE (sighting density) and DPSE (porpoise density) values would be deduced for evaluation on level of porpoise usage. First, positions of on-effort porpoise sightings from the study period are plotted onto 68 grids (1 km x 1 km each) within the survey area. Sighting density grids and porpoise density grids shall then be normalized with the amount of survey effort conducted within each grid. The total amount of survey effort spent on each grid shall be calculated by examining the survey coverage on each line-transect survey to determine how many times the grid had been surveyed during study period. With the amount of survey effort calculated for each grid, the sighting density and porpoise density of each grid shall be further normalized (i.e. divided by the unit of survey effort).
The newly-derived unit for sighting density was termed SPSE, representing the number of on-effort sightings per 100 units of survey effort. In addition, the derived unit for actual porpoise density was termed DPSE, representing the number of dolphins/porpoise per 100 units of survey effort. Among the 1-km2 grids that were partially covered by land, the percentage of sea area was calculated using GIS tools, and their SPSE and DPSE values were adjusted accordingly. The following formulae shall be used to estimate SPSE and DPSE in each 1-km2 grid within the study area:
SPSE = ((S / E) x 100) / SA%
DPSE = ((D / E) x 100) / SA%
where S = total number of on-effort sightings
D = total number of dolphins/porpoises from on-effort sightings
E = total number of units of survey effort
SA% = percentage of sea area
6.2.2 Passive Acoustic Monitoring (PAM)The PAM aims to study the usage of an area by Finless Porpoise by using an array of automated static porpoise detectors (e.g. C-POD) which would be deployed at different locations to detect the unique ultra-high frequency sounds produced by Finless Porpoise. During the construction period, the PAM survey will be conducted including placement of two passive porpoise detectors outside the Project Area as control site (i.e. within Pui O Wan and to the south of Tai A Chau) and one porpoise detector within the Project Area (i.e. near Shek Kwu Chau) as shown in Figure 6.2 below.
|
These three detectors will be deployed on-site to carry out 24-hours monitoring for a period listed as Table 6.2 below during the construction phase.
Table 6.2 PAM Deployment Period
Season |
Months |
Deployment Period |
Peak Season |
December, January, February, March, April or May |
At least 30 days during the peak months of porpoise occurrence in South Lantau waters |
The automated static porpoise detectors shall detect the presence and number of finless porpoise and Chinese White Dolphins respectively over the deployment period, with the false signal such as boat sonar and sediment transport noise distinguished and filtered out. The detectors shall be deployed and retrieved by professional dive team on the seabed of the three selected location shown in Figure 6.2. During each deployment, the C-POD unit serial numbers as well as the time and date of deployments shall be recorded. Information including the GPS positions and water depth at each of the deployment locations shall also be obtained.
The diel patterns (i.e. 24-hour activity pattern) of finless porpoise occurrence among the three sites at Shek Kwu Chau, Tai A Chau and Pui O Wan shall be analyzed. Peaks and troughs of finless porpoise occurrence per hour of day would be identified and compared with the results obtained from pre-construction monitoring.
6.2.3 Land-based Theodolite TrackingThe Land-based Theodolite Tracking study would use the same station as in the AFCD monitoring study(same as the baseline monitoring location), which is situated at the southwest side of Shek Kwu Chau (GPS position: 22o11.47 N and 113o59.33 E) as shown in below Figure 6.3. The station was selected based on its height above sea level (at least 20 metres), close proximity to shore, and relatively unobstructed views of the entire Project Area to the southwest of Shek Kwu Chau. The height of the Shek Kwu Chau Station established by the HKCRP team is 74.6 m high at mean low water, and only a few hundred metres to the IWMF reclamation site, which is ideal for the purpose for the present behavioural and movement monitoring of finless porpoises as well during construction phase considering there as an un-obstructed vantage point at a height above the Project Site.
|
Figure 6.3 Locations of Land-based Theodolite Tracking |
During the construction phase, Land-based Theodolite Tracking will be carried out for approximately six hours of tracking for each day of field work for a period listed as Table 6.3 below, preferably at the initial stage of the construction period (i.e. December 2018 to May 2019).
Table 6.3 Land-based Theodolite Tracking Survey Period
Season |
Months |
Survey Period |
Peak Season |
December, January, February, March, April or May |
30 days during the peak months of porpoise occurrence in South Lantau waters |
The monitoring period for land-based theodolite tracking will be proposed to be overlapped with the PAM. The monitoring team consists of one experienced theodolite operator and at least two field observers for assistance. To conduct theodolite tracking, our observers will search systematically for Finless Porpoise using the unaided eye and 7 x 50 handheld binoculars on each survey day throughout the study area. When an individual or group of porpoises is located, a theodolite tracking session will be initiated and focal follow methods will be used to track the porpoise(s). Behavioural state data (i.e. resting, milling, travelling, feeding and socializing) shall also be recorded every 5 minutes for the focal individual or group. Positions of porpoises and boats shall be measured using a digital theodolite connected to a laptop computer. This tracking survey will be conducted during the peak season between December 2018 and May 2019 for 30 surveys spanning across 15-16 weeks during the peak season to provide good temporal coverage during the initial stage of the construction period.
6.3 Specific Mitigation Measures 6.3.1 Monitored exclusion zonesDuring the installation/re-installation/relocation process of floating type silt curtains, in order to avoid the accidental entrance and entrapment of marine mammals within the silt curtains, a monitored exclusion zone of 250 m radius from silt curtain should be implemented. The exclusion zone should be closely monitored by an experienced marine mammal observer (MMO) for at least 30 minutes before the start of installation/re-installation/relocation process. If a marine mammal is noted within the exclusion zone, all marine works should stop immediately and remain idle for 30 minutes, or until the exclusion zone is free from marine mammals. The experienced marine mammal observer should be well trained to detect marine mammals. Binoculars should be used to search the exclusion zone from an elevated platform with unobstructed visibility. The marine mammal observer(s) shall be independent of the construction contractor and shall form part of the Environmental Team and have the power to call-off construction activities.
According to the Condition 2.25 of the FEP, MMEZ should be implemented during the installation/re-installation/relocation process of floating type silt curtains in order to avoid the accidental entrance and entrapment of marine mammals within the silt curtains. Also, marine construction works expected to produce underwater acoustic disturbance as per Condition 2.27 of the FEP, especially within December and May, would require the implementation of MMEZ, which currently all those specific construction activities have been replaced by less acoustically disturbing construction methods such as Deep Cement Mixing (DCM) and Precast Concrete Blocks Installation as discussed in Section 5.3 of the Detailed Monitoring Programme on Finless Porpoise, however, MMEZ would also be implemented for precautionary purpose for DCM works.
A MMEZ with 250 m distance from the boundary of a work area shall be established during the above situation. A typical MMEZ is indicated in Figure 6.4 for reference. The MMEZ serves as a monitoring approach to provide appropriate and immediate actions once finless porpoise or Chinese White Dolphin is sighted within the MMEZ. All MMEZ will be monitored by competent Marine Mammal Observers (MMOs) to be provided by the Environmental Team (ET) for the IWMF and trained by the Marine Mammal Monitoring Specialist of the ET who is independent from JV.
|
Figure 6.4 Illustration of Typical MMEZ |
Prior to the commencement of construction activity, our MMOs shall ensure the boundary of a marine work area and setting up of the MMEZ for the work area and get access to the monitoring location on a barge or a lookout point where there is no obstructed views for monitoring the MMEZ during the construction activity. The MMEZ shall be scanned thoroughly by a MMO for any presence of marine mammal e.g. finless porpoise for an initial period of 30 minutes. Construction activity shall only be commenced after the MMO has confirmed that the MMEZ is clear of the marine mammal for the initial period of 30 minutes. The MMO shall then inform the construction superintendent through mobile phone or handheld transceivers to certify the commencement of construction activity. The MMEZ monitoring shall be carried on throughout the period for all active construction activities requiring implementation of MMEZ.
When any mammal marine, e.g. Finless Porpoise, is detected by the MMO within the MMEZ during construction, the MMO shall inform the construction superintendent immediately through mobile phone or handheld transceivers to cease construction activity within the MMEZ. Construction activity shall not be re-commenced until the MMO confirms that the MMEZ is continuously clear of marine mammal for a period of 30 minutes. The MMO shall then inform the construction superintendent through mobile phone or handheld transceivers to certify the re-commencement of construction activity.
As there could be a number of Contractors working at the same time within a work area for the IWMF project, a full contact list of MMEZ monitoring team members of the ET and the relevant responsible construction superintendents of the Contractor at the site shall be prepared, updated regularly and circulated to all parties involved in the MMEZ monitoring. With a full contact list, our MMOs shall be able to find out the contacts of corresponding persons in case of marine mammal sighting within and near the MMEZ or emergent occurrence of any unpredictable impact on marine mammal.
If a marine mammal is still observed in close vicinity but outside the MMEZ, the MMO shall inform the construction superintendent about the presence of marine mammal. The MMO shall remain in position and closely observe the movement of the marine mammal as well as searching for the appearance of any other marine mammal within the MMEZ. No matter the marine mammal is observed within or in close vicinity but outside the MMEZ, the construction superintendent or relevant persons shall inform all vessel captains involved in construction activities around the MMEZ to pay special attention of the presence of the marine mammal in order to reduce chance of collision with them. In case of injury or live-stranded marine mammal being found within the MMEZ, the marine mammal observer shall immediately inform the construction superintendent to suspend construction activities within the works area and contact AFCD through 1823 marine mammal stranding hotline.
6.3.2 Marine mammal watching planUpon the completion of silt curtain installation/re-installation/relocation, all marine works would be conducted within a fully enclosed environment within the silt curtain. Hence exclusion zone monitoring would no longer be required. Subsequently, a marine mammal watching plan would be implemented.
Before commencement of dredging/sand blanket laying work at each designated area, a trained MMO shall check whether position frame silt curtains are ready, well prepared and operated without any obvious damage. Also, the MMO shall confirm the presence of the relevant frontline staff of the main contractor or its sub-contractors and engineers on board to ensure the effective communication, coordination and implementation of the response plan in relation to any incidents involving marine mammals within the waters surrounded by the position frame type silt curtains and the work areas. Also, there are lookout points at an elevated level on each barge, clear and safe access at the edges of the derrick lighter/ flag-top barge for inspection during dredging/sand blanket laying works, provision of sufficient lighting is required if working at night.
During the operation, the inspection will be conducted daily. The MMO will walk along the edge of derrick lighter (DL) and flag-top barge (FB) along the position frame silt curtain or proper location without obstacles where appropriate to inspect the position frame silt curtain with naked eyes, the MMO will check that the position frame silt curtains are maintained in the correct positions with no obvious defects / entanglement and there is no observable muddy water passing through the position frame silt curtain system. Any floating refuse trapped by the silt curtain shall be removed as part of the regular inspection. For night inspection, spotlight will be used to provide sufficient brightness to assist the inspection in dark condition.
For the localized silt curtain re-deployment, MMO will conduct visual inspection to confirm that there is no presence of marine mammal within the localized silt curtain. Visual inspection will be conducted every an hour by MMO till confirming that there is not any marine mammal observed in the surrounding area of the frame type silt curtain. The duration will be subject to various conditions, e.g. weather or angle of observation. The works can only commence after confirming that the surrounding waters of the localized silt curtains has not contain any marine mammal. Thereafter, frontline staff, i.e. foremen, site agent, superintendents and engineers will assist our MMO in implementing the plan from the active work fronts within the waters surrounded by the silt curtains throughout the work period. The MMO will conduct regular check every 60 minutes to observe the presence of any marine mammal around the localized silt curtain or being trapped by the localized silt curtain. The MMOs will also check if the localized silt curtains are in correct positions..
The MMO shall fill up our Marine Mammal Sighting Record Sheet. After inspection, those records should be kept properly and submitted to the project team. In case there is any marine mammal being found, the MMO should carry out the response actions and communicate with relevant parties to stop and then resume work after the discovered marine mammal leaves. After lifting up and mobilization of silt curtain, the MMO will repeat the procedures of regular and visual inspection until the end of the construction works.
Details of the lookout points at derrick lighter (DL) and flat-top barge (FB) for dredging/sand blanket filling are shown in Figure 6.4 and Figure 2.2 respectively. Each lookout point will have an unobstructed view to waters around the DL and FB. The MMO will move around the DL and FB to establish a clear and unobstructed view as much as they can without compromising the safety concern. When appropriate, the lookout point can be replaced by a proper location if unobstructed view can be assured.
6.4 Results and Observations 6.4.1 Vessel-based Line-transect Survey The monthly survey was conducted on 23 July 2018. As this is the designated off-peak season (June-November), only one survey was completed. A total on effort (transects only) survey length of 36.9km was completed, 17.4km at Beaufort Sea State 2 or better (Table 6.4). No sightings of marine mammals were recorded.Table 6.4 Summary of Vessel-based Line-transect Survey Effort
Date |
Area* |
Beaufort |
Effort (km) |
Season |
Vessel |
Effort Type** |
23-Jul-18 |
SEL |
2 |
19.5 |
SUMMER |
SMRUHK |
P |
23-Jul-18 |
SEL |
3 |
17.4 |
SUMMER |
SMRUHK |
P |
* As shown in Figure. 6.1
** P (from AFCD) denotes the ON EFFORT survey on the transect line, not the adjoining passages
A review of the long term AFCD marine mammal monitoring programme, the EIA and the pre-construction baseline monitoring report for this project was conducted. Both the EIA and the pre-construction baseline monitoring were conducted during the peak porpoise months (Dec 2008 to May 2009 and Feb-April 2018, respectively), and, as such, these data are not directly comparable to this survey month which is a porpoise off-peak month. Therefore, a comparison can only be made to the AFCD long term marine mammal monitoring data. A review of the Beaufort Sea state survey conditions for July 2017 (AFCD Monitoring Report) calculated that 60% of July 2017 surveys were conducted at Beaufort Sea State 2 or better. For this project in July 2018, 53% surveys were conducted at Beaufort Sea State 2 or better and, as such, survey conditions across years are comparable. A review of the porpoise sightings in the survey area for July 2017 show that one (1) sighting of a single (1) porpoise was recorded. Given the similar survey conditions and the extremely low encounter rate recorded for porpoise in the project area during this survey month, no sightings within this area in July 2018 is not deemed to be significantly different from normal, with reference to the AFCD long term marine mammal monitoring data. It is difficult to draw conclusions with regards to impacts on marine mammals as predicted in the EIA and the effectiveness of project mitigation measures during the initial phase of construction activities when porpoise sightings are typically rare (e.g., 1 individual) during the survey month. As surveys continue for this project, data shall be constantly re-evaluated across survey months to discern trends and impacts, if any. 6.4.2 PAM and Land-based Theodolite Tracking These tracking surveys will be conducted during the peak season between December 2018 and May 2019 for 30 surveys spanning across 15-16 weeks during the peak season to provide good temporal coverage during the initial stage of the construction period. 6.4.3 Specific Mitigation Measures Silt curtains were deployed for sand blanket laying works and DCM trial during the reporting period. At least two MMO were on duty for continuous monitoring of the Marine Mammal Exclusion Zone (MMEZ) for DCM trial works and installation/re-installation/relocation process of silt curtains, and the marine mammal trapping checking and silt curtains inspection in accordance with the Detailed Monitoring Programme of Finless Porpoise and Marine Mammal Watching Plan respectively. Trainings for the MMO were provided by the ET prior to the aforementioned works, with a cumulative total of 12 individuals being trained and the training records kept by the ET. From the Marine Mammal Watching observation records and MMEZ monitoring log records, no Finless Porpoise or other marine mammals were observed within or around the MMEZ and silt curtains in the reporting month.7. White-Bellied Sea Eagle 7.1 Monitoring Requirement 7.1.1 On Shek Kwu Chau Island, a nest of WBSE is located about 60 m above ground within a hillside shrubland habitat, 130 m in-land from shore, about 550 m away from the proposed reclaimed land, with no human access. 3 phases monitoring programme will be comprise including: pre-construction phase, construction phase and operation phase. 7.1.2 The Pre-Construction WBSE monitoring was started on 30 January 2018 and the location of WBSE nest was confirmed on 21 February 2018 and it is located at the western part of SKC Island (Figure 1). Two adults and two chicks were also recorded on 5th March 2018 survey till the end of the Pre-construction monitoring on 15th May 2018. Construction Phase monitoring were carried out followed by the commencement of the Construction Phase on 28th June 2018. 7.2 WBSE Monitoring Parameters, Time, Frequency 7.2.1 The objective of the construction phase monitoring should be to verify the utilisation of the area by WBSE, their responses to construction disturbance, as well as the effectiveness of the proposed mitigation measures. Throughout the construction phase, field surveys should be conducted twice per month during their core breeding season (from December to May), and once per month outside their core breeding season (from June to November). The monitoring frequency should be increased to weekly during the incubation period of each year. In order to confirm their foraging ground near the construction site, it is necessary to conduct daily monitoring during the first week of nestling period in each year. The monitoring schedule during the reporting period is provided in Appendix C. 7.3 Monitoring Location 7.3.1 Since there is no suitable land-based along the coast of SKC, only boat surveys were conducted. On Shek Kwu Chau Island, a nest of WBSE is located about 60 m above ground within a hillside shrubland habitat, 130 m in-land from shore, about 550 m away from the proposed reclaimed land, with no human access. 7.4 Monitoring Methodology 7.4.1 Information to be collected included feeding, perching/roosting, preening, soaring, flying, nesting and territorial guarding and the time spent on each activity. The responses and reactions to any disturbance to the WBSEs were also recorded and examined in conjunction with the construction noise and/or other events in the vicinity. Other disturbances such as weather condition, or invasion by other fauna species were also recorded. 7.4.2 Binocular, scope, camera, lens and GPS device used are summarized as Table 7.1 below:
Table 7.1 List of Equipment Used during Construction Phase Monitoring
Equipment |
Quantity |
Swarovski EL 8.5 x 42 Binocular |
1 |
Swarovski EL Range 8 x 42 Binocular |
1 |
Swarovski ATX 25-60 x 85 Spotting Scope |
1 |
Canon 1Dx Mark II Camera |
1 |
Canon EF300mm F2.8 Lens with Canon 2x Teleconverter |
1 |
Canon PowerShot G7X Camera |
1 |
Garmin GPSMAP 64S |
1 |
Table 7.2 Weather Conditions during the WBSE Monitoring
Date |
Condition |
Temperature (℃) |
26 July 2018 |
- Moderate south-easterly winds - Wind strength from Beaufort force 4 to 5 - Mainly cloudy with a few showers |
30.0 |
Figure 7.1 Location of WBSE Nest on SKC
7.5.3 No invasion of other fauna species was recorded and no sign of using the construction site as a foraging ground was not recorded as well. 7.5.4 During the first month construction phase monitoring, no abnormal behaviour of the recorded adult was shown. All marine works during the first month construction period did not show any influence to the WBSE. 7.5.5 A construction phase monitoring will be continued outside their core breeding season (between June to November) in order to monitor the utilization of the area by WBSE and their responses to construction disturbance.
Figure 8.1 Environmental Complaint Handling Procedure
Table 8.1 Summary of SS Compliance Status at Impact Stations (Mid-Ebb Tide)
Date |
B1 |
B2 |
B3 |
B4 |
CR1 |
CR2 |
F1 |
H1 |
S1 |
S2 |
S3 |
M1 |
29-6-2018 |
|
|
|
|
|
|
|
|
|
|
|
|
3-7-2018 |
|
|
|
|
|
|
|
|
|
|
|
|
5-7-2018 |
|
|
|
|
|
|
|
|
|
|
|
|
7-7-2018 |
|
|
|
|
|
|
|
|
|
|
|
|
10-7-2018 |
|
|
|
|
|
|
|
|
|
|
|
|
12-7-2018 |
|
|
|
|
|
|
|
|
|
|
|
|
14-7-2018 |
|
|
|
|
|
|
|
|
|
|
|
|
16-7-2018 |
|
|
|
|
|
|
|
|
|
|
|
|
18-7-2018 |
|
|
|
|
|
|
|
|
|
|
|
|
20-7-2018 |
|
|
|
|
|
|
|
|
|
|
|
|
23-7-2018 |
|
|
|
|
|
|
|
|
|
|
|
|
25-7-2018 |
|
|
|
|
|
|
|
|
|
|
|
|
27-7-2018 |
|
|
|
|
|
|
|
|
|
|
|
|
30-7-2018 |
|
|
|
|
|
|
|
|
|
|
|
|
No. of SS Exceedances |
|
|
|
|
|
|
|
|
|
|
|
|
Note: Detailed results are presented in Appendix D
Legend:
|
No exceedance of Action Level and Limit Level |
|
Exceedance of Action Level recorded at monitoring station located downstream of the Project based on dominant tidal flow |
|
Exceedance of Action Level recorded at monitoring station located upstream/unrelated stream (neither upstream nor downstream, far away) of the Project based on dominant tidal flow |
|
Exceedance of Limit Level recorded at monitoring station located downstream of the Project based on dominant tidal flow |
|
Exceedance of Limit Level recorded at monitoring station located upstream/unrelated stream of the Project based on dominant tidal flow |
|
Upstream/unrelated stream station with respect to IWMF Project during the respective tide based on dominant tidal flow |
|
Cancelled due to adverse weather |
Table 8.2 Summary of SS Compliance Status at Impact Stations (Mid-Flood Tide)
Date |
B1 |
B2 |
B3 |
B4 |
CR1 |
CR2 |
F1 |
H1 |
S1 |
S2 |
S3 |
M1 |
29-6-2018 |
|
|
|
|
|
|
|
|
|
|
|
|
3-7-2018 |
|
|
|
|
|
|
|
|
|
|
|
|
5-7-2018 |
|
|
|
|
|
|
|
|
|
|
|
|
7-7-2018 |
|
|
|
|
|
|
|
|
|
|
|
|
10-7-2018 |
|
|
|
|
|
|
|
|
|
|
|
|
12-7-2018 |
|
|
|
|
|
|
|
|
|
|
|
|
14-7-2018 |
|
|
|
|
|
|
|
|
|
|
|
|
16-7-2018 |
|
|
|
|
|
|
|
|
|
|
|
|
18-7-2018 |
|
|
|
|
|
|
|
|
|
|
|
|
20-7-2018 |
|
|
|
|
|
|
|
|
|
|
|
|
23-7-2018 |
|
|
|
|
|
|
|
|
|
|
|
|
25-7-2018 |
|
|
|
|
|
|
|
|
|
|
|
|
27-7-2018 |
|
|
|
|
|
|
|
|
|
|
|
|
30-7-2018 |
|
|
|
|
|
|
|
|
|
|
|
|
No. of SS Exceedances |
|
|
|
|
|
|
|
|
|
|
|
|
Note: Detailed results are presented in Appendix D
Legend:
|
No exceedance of Action Level and Limit Level |
|
Exceedance of Action Level recorded at monitoring station located downstream of the Project based on dominant tidal flow |
|
Exceedance of Action Level recorded at monitoring station located upstream/unrelated stream (neither upstream nor downstream, far away) of the Project based on dominant tidal flow |
|
Exceedance of Limit Level recorded at monitoring station located downstream of the Project based on dominant tidal flow |
|
Exceedance of Limit Level recorded at monitoring station located upstream/unrelated stream of the Project based on dominant tidal flow |
|
Upstream/unrelated stream station with respect to IWMF Project during the respective tide based on dominant tidal flow |
|
Cancelled due to adverse weather |
8.4 No project-related Action Level & Limit Level exceedance was recorded during the reporting period. 8.5 No notification of summons and prosecution was received in the reporting period. 8.6 Statistics on complaints, notifications of summons and successful prosecutions are summarized in Appendix O.
9. EM&A Site Inspection 9.1 Site inspections were carried out on a weekly basis to monitor the implementation of proper environmental pollution control and mitigation measures under the Contract. In the reporting period, site inspections were carried out on 3, 10, 20 and 24 July 2018 at the site portions list in Table 9.1 below.
Table 9.1 Site Inspection Record
Date |
Inspected Site Portion |
Time |
3 July 2018 |
Portion 7 (Tung Chung) |
09:00-10:30 |
10 July 2018 |
Portion 7 (Tung Chung) |
09:00-10:30 |
20 July 2018 |
Portion 1, 1A&1B (near SKC) |
09:30-11:30 |
24 July 2018 |
Portion 1, 1A&1B (near SKC) |
09:00-11:00 |
i. Portion 7 is the site at Tung Chung for stockpiling of building materials
ii. Portion 1, 1A&1B are the sites near SKC at location shown at Figure 1.1
9.2 One joint site inspection with IEC was carried out on 20 July 2018. 9.3 Minor deficiencies were observed during weekly site inspection. Key observations during the site inspections are summarized in Table 9.2.Table 9.2 Site Observations
Date |
Environmental Observations |
Follow-up Status |
3 July 2018 |
Observation(s) and Recommendation(s) 1. Rubbish at the entrance of Portion 7 should be cleaned |
1. Rubbish was removed. |
10 July 2018 |
Observation(s) and Recommendation(s) 1. Stagnant water at Portion 7 should be removed |
1. Stagnant water was removed |
20 July 2018 |
No special observation and recommendation |
- |
24 July 2018 |
Observation(s) and Recommendation(s) 1. On DCM barge, drummed chemicals should be put on drip tray. 2. General refuse should be removed to maintain good house keeping. |
1. chemical drums were removed 2. General refuse has been removed. |
10. Future Key Issues 10.1 Works to be undertaken in the next reporting month are:
· Marine Site Investigation Works
· Laying Geotextile and Sand Blanket for Static Loading Test
· Static Loading Test
10.2 Potential environmental impacts arising from the above construction activities are mainly associated with water quality, construction noise, waste management and ecology. 10.3 The key environmental mitigation measures for the Project in the coming reporting period expected to be associated with the construction activities include:· Reduction of noise from equipment and machinery on-site;
· Installation of silt curtains for the sand blanket laying works;
· Sorting, recycling, storage and disposal of general refuse and construction waste;
· Management of chemicals and avoidance of oil spillage on-site; and
· Implementation of MMEZ and inspection of enclosed environment within silt curtains as per DMPFP
10.4 The tentative schedule of regular construction noise, water quality and ecology monitoring in the next reporting period is presented in Appendix P. The regular construction noise, water quality and ecology monitoring will be conducted at the same monitoring locations in the next reporting period.11. Conclusion and Recommendations 11.1 This 1st monthly Environmental Monitoring and Audit (EM&A) Report presents the EM&A works undertaken during the period from 28 June 2018 to 31 July 2018 in accordance with the Updated EM&A Manual and the requirement under EP- 429/2012/A and FEP-01/429/2012/A. 11.2 Construction noise, water quality, construction waste, coral, marine mammal and White-Bellied Sea Eagle (WBSE) monitoring were carried out in the reporting period. No project-related exceedance of the Action and Limit Level was recorded during the reporting period. All monitoring results implied that the effectiveness and efficiency of the mitigation measures are satisfactory. 11.3 Weekly environmental site inspection was conducted during the reporting period. Minor deficiencies were observed during site inspection and were rectified. The environmental performance of the Project was therefore considered satisfactory. 11.4 According to the environmental site inspections performed in the reporting month, the Contractor is reminded to pay attention on maintaining site tidiness and proper materials storage. 11.5 No environmental complaint was received in the reporting period. 11.6 No notification of summons or prosecution was received since commencement of the Contract. 11.7 The ET will keep track on the construction works to confirm compliance of environmental requirements and the proper implementation of all necessary mitigation measures.