Revision History
C |
Updated Appendix D |
8 March 2024 |
B |
Revision based on EPD¡¦s comment |
15 August 2019 |
A |
First Submission |
13 April 2019 |
Rev. |
Description of Modification |
Date |
Content
2. Marine Water Quality Monitoring
8 Summary of Monitoring Exceedance, Complaints, Notification of Summons and Prosecutions
10. Conclusion and Recommendations
Appendix A |
|
Appendix B |
Summary of Implementation Status of Environmental Mitigation |
Appendix C |
|
Appendix D |
|
Appendix E |
|
Appendix F |
|
Appendix G |
|
Appendix H |
|
Appendix I |
Executive Summary
A1. The Project, Integrated Waste Management Facility (IWMF), is a Designated Project under the Environmental Impact Assessment Ordinance (Cap. 499) (EIAO) and is currently governed by a Further Environmental Permit (FEP No. FEP-01/429/2012/A) for the construction and operation of the Project.
A2. In accordance with the Updated Environmental Monitoring and Audit (EM&A) Manual for the Project, EM&A works for marine water quality, noise, waste management and ecology should be carried out by Environmental Team (ET), Acuity Sustainability Consulting Limited (ASCL), during the construction phase of the Project.
A3. This is the 3rd Quarterly EM&A Report, prepared by ASCL, for the Project summarizing and concluding the monitoring results and audit findings of the EM&A programme at and around Shek Kwu Chau (SKC) during the reporting period from 1 January 2019 to 31 March 2019.
A4. The EM&A works for construction noise, water quality, construction waste, coral, marine mammal and White-Bellied Sea Eagle (WBSE) were conducted during the reporting period in accordance with the Updated EM&A Manual.
A5. Weekly site inspections of the construction works were carried out by ET to audit the mitigation measures implementation status. Monthly joint site inspections were carried out by ET and IEC.
1. Basic Project Information 1.1.1 This is the 3rd Quarterly EM&A Report for the Project which summarizes the key findings of the EM&A programme during the reporting period from 1 January 2019 to 31 March 2019. 1.1.2 The Project Organization structure for Construction Phase is presented in Figure 1.1. 1.1.3 Contact details of the key personnel are presented in Table 1.1 below:
Table 1.1 Contact Details of Key Personnel
Party |
Position |
Name |
Telephone no. |
Environmental Protection Department |
Project Proponent |
Cheng Tak-Kuen |
2594-6111 |
Keppel Seghers ¡V Zhen Hua Joint Venture |
Project Manager |
Kenny Yu |
2192-0606 |
Acuity Sustainability Consulting Limited |
Environmental Team Leader |
Robin Ho |
2698-6833 |
ERM-Hong Kong, Limited |
Independent Environmental Checker |
Mandy To |
2271-3000 |
1.3. Summary of Construction Works
1.1.4 Details of the major construction activities undertaken in this reporting period are shown in Table 1.2 below. The construction programme is presented in Appendix A.Table 1.2 Summary of the Construction Activities Undertaken during the Reporting Period
Location of works |
Construction activities undertaken |
Remarks on progress |
Seawall and breakwater locations |
¡P Marine site investigation works |
¡P Completed |
Location of DCM Site Trial |
¡P Coring of DCM samples |
¡P Completed |
Seawall locations |
¡P Collecting of Marine Sediment Samples |
¡P Completed |
Location of DCM Static Loading Test |
¡P DCM installation |
¡P Completed |
Seawall and berth area |
¡P Laying of Geotextile and Sand Blanket |
¡P 73 out of 95 geotextiles were laid ¡P Completed for sand blanket laying |
Seawall and berth area |
¡P DCM installation ¡P Dredging operation |
¡P On-going |
Table 1.3 Summary of Status for Key Environmental Aspects under the Updated EM&A Manual
1.1.6 Other than the EM&A works by ET, environmental briefings, trainings and regular environmental management meetings were conducted, in order to enhance environmental awareness and closely monitor the environmental performance of the contractors. 1.1.7 The EM&A programme has been implemented in accordance with the recommendations presented in the approved EIA Report and the Updated EM&A Manual. A summary of updated implementation status of the environmental mitigation measures for the construction phase of the Project during the reporting period is provided in Appendix B.
2. Marine Water Quality Monitoring 2.1.1 Measurement of Dissolved Oxygen (DO), Turbidity, Suspended Solids (SS), Salinity and pH have been undertaken at the eleven monitoring stations during general water quality monitoring. Besides the above parameters, monitoring of Total Alkalinity, Current Velocity and Current Direction have been undertaken at all fourteen monitoring stations (including S1, S2 and S3) during regular DCM monitoring. 2.1.2 Current velocity and direction, DO, temperature, salinity, turbidity and pH were measured in-situ and the SS, Total Alkalinity were assayed in a HOKLAS laboratory. 2.1.3 In associate with the water quality parameters, other relevant data were also measured, such as monitoring location/position, time, water depth, sampling depth, tidal stages, weather conditions and any special phenomena or work underway nearby were also recorded. 2.1.4 The initial intensive DCM monitoring programme has been conducted daily from 11 February to 24 February 2019 and conducted every two days from 25 February to 10 March 2019. The actual duration of the initial DCM monitoring might extend beyond four weeks should there be any exceedances in specific-DCM parameters (Temperature & Alkalinity) of water quality action and limit levels. 2.1.5 Table 2.1 summarizes the monitoring parameters, frequency and duration of the impact water quality monitoring.
Table 2.1 Water Quality Monitoring Parameters, Frequency and Duration
Parameter, unit |
Frequency |
No. of Depths |
¡P Water Depth(m) ¡P Temperature(oC) ¡P Salinity(ppt) ¡P pH (pH unit) ¡P Dissolved Oxygen (DO)(mg/L and % of saturation) ¡P Turbidity(NTU) ¡P Suspended Solids (SS), mg/L ¡P Total alkalinity ¡P Current velocity ¡P Direction |
General water quality monitoring and Regular DCM monitoring: 3 days per week, at mid-flood and mid-ebb tides
*Intensive DCM monitoring: Daily in first 2 weeks, at mid-flood and mid-ebb tides. if no exceedance is recorded within the first two weeks, then the monitoring frequency can be reduced to every two days. |
3 water depths: 1m below sea surface, mid-depth and 1m above sea bed. If the water depth is less than 3m, mid-depth sampling only. If water depth is less than 6m, mid-depth may be omitted.
|
2.2 Water Quality Monitoring Locations
2.2.1 Impact water quality monitoring was conducted at eleven monitoring locations during general water quality monitoring and fourteen water monitoring locations during regular DCM monitoring, as shown in Figure 2.1.
Figure 2.1 Water monitoring locations at Artificial Island near SKC |
Figure 2.2 Water monitoring locations during intensive DCM monitoring
2.3.1 Based on the baseline monitoring data and the derivation criteria specified in the Updated EM&A Manual and Detailed Plan on Deep Cement Mixing, the Action/Limit Levels are presented in Table 2.2.Table 2.2 Derived Action and Limit Levels for Water Quality Monitoring (Dry Season)
Parameters |
Action |
Limit |
Construction Phase Impact Monitoring |
||
DO in mg/L |
≤ 7.13 |
≤ 4 |
SS in mg/L |
≥ 8 or 120% of control station¡¦s SS at the same tide of the same day of measurement, whichever is higher |
≥ 10 or 130% of control station's SS at the same tide of the same day of measurement, whichever is higher |
Turbidity in NTU |
≥ 5.6 or 120% of control station¡¦s turbidity at the same tide of the same day of measurement, whichever is higher |
≥ 12.81 or 130% of control station's turbidity at the same tide of the same day of measurement, whichever is higher |
Temperature in¢XC |
1.8¢XC above the temperature recorded at representative control station at the same tide of the same day |
2¢XC above the temperature recorded at representative control station at the same tide of the same day |
Total Alkalinity in mg/L |
≥116 or 120% of control station¡¦s Total Alkalinity at the same tide of the same day of measurement, whichever is higher |
≥ 118 or 130% of control station¡¦s Total Alkalinity at the same tide of the same day of measurement, whichever is higher |
Notes:
i. "Depth-averaged" is calculated by taking the arithmetic means of reading of all three depths.
ii. For DO, non-compliance of the water quality limits occurs when monitoring result is lower than the limits.
iii. For turbidity, SS and Salinity, non-compliance of the water quality limits occurs when monitoring result is higher than the limits.
2.3.2 The Action and Limit (AL) levels for DCM-specific and other water quality parameters during initial intensive DCM monitoring with referring to Detailed Plan on Deep Cement Mixing, as shown in Table 2.3 and 2.4 below respectively.Table 2.3 Action and Limit Levels for DCM-specific Water Quality Parameters (Intensive DCM Monitoring)
Parameters |
Action |
Limit |
Construction Phase Impact Monitoring |
||
Temperature in¢XC |
1.8¢XC above the temperature recorded at representative control station at the same tide of the same day |
2¢XC above the temperature recorded at representative control station at the same tide of the same day |
Total Alkalinity in mg/L
|
95 percentile of baseline data or 120% of representative control station at the same tide of the same day, whichever is higher |
99 percentile of baseline data or 130% of representative control station at the same tide of the same day, whichever is higher |
Notes:
i. "Depth-averaged" is calculated by taking the arithmetic means of reading of all three depths.
ii. For Temperature and Total Alkalinity, non-compliance of the water quality limits occurs when monitoring result is higher than the limits.
Table 2.4 Action and Limit Levels for Other Water Quality Parameters (Intensive DCM Monitoring)
Parameters |
Action |
Limit |
Construction Phase Impact Monitoring |
||
DO in mg/L (Surface and middle) |
80% of representative control station at the same tide of the same day or 4mg/L, whichever is lower. |
70% of representative control station at the same tide of the same day or 4mg/L, whichever is lower. |
DO in mg/L (Bottom) |
80% of representative control station at the same tide of the same day or 2mg/L, whichever is lower. |
70% of representative control station at the same tide of the same day or 2mg/L, whichever is lower. |
SS in mg/L |
120% of representative control station at the same tide of the same day. |
130% of representative control station at the same tide of the same day. |
Turbidity in NTU |
Notes:
i. "Depth-averaged" is calculated by taking the arithmetic means of reading of all three depths.
ii. For DO, non-compliance of the water quality limits occurs when monitoring result is lower than the limits.
iii. For SS and Turbidity, non-compliance of the water quality limits occurs when monitoring result is higher than the limits.
2.4 Monitoring Results and Observations
2.4.1 DCM injection works and sand blanket laying works were conducted during the reporting period, thus both general water quality monitoring at the eleven monitoring stations and general DCM monitoring including monitoring stations S1, S2 and S3 were conducted. Monitoring results of 7 key parameters: Salinity, DO, turbidity, SS, pH, temperature and total alkalinity in each month of this reporting period, are summarized in Table 2.5, and results trending are presented graphically in Appendix C. 2.4.2 During the reporting period, initial intensive DCM water quality monitoring was conducted between 25 February to 10 March 2019 at all twelve monitoring stations consisting of UC1, UC2 and I1 to I10. Monitoring results of 7 key parameters: Salinity, DO, turbidity, SS, pH, temperature and total alkalinity for initial intensive DCM monitoring in this reporting month, are summarized in Table 2.6, and details results are presented in Appendix C.Table 2.5 Summary of Regular DCM Impact Water Quality Monitoring Results
Locations |
Parameters |
||||||||||||||||||||||||
Salinity (ppt) |
Dissolved Oxygen (mg/L) |
pH |
Turbidity (NTU) |
Suspended Solids (mg/L) |
Temp. (oC) |
Total Alkalinity (mg/L) |
|||||||||||||||||||
Surface & Middle |
Bottom |
||||||||||||||||||||||||
Jan |
Feb |
Mar |
Jan |
Feb |
Mar |
Jan |
Feb |
Mar |
Jan |
Feb |
Mar |
Jan |
Feb |
Mar |
Jan |
Feb |
Mar |
Jan |
Feb |
Mar |
Jan |
Feb |
Mar |
||
B1 |
Avg. |
30.19 |
30.70 |
30.60 |
9.16 |
10.48 |
10.56 |
9.15 |
10.52 |
10.54 |
8.15 |
8.43 |
8.93 |
4.3 |
3.4 |
2.5 |
6.69 |
4.28 |
5.23 |
20.1 |
21.2 |
20.8 |
112.9 |
111.8 |
110.3 |
Min. |
29.04 |
29.36 |
27.45 |
8.23 |
8.70 |
7.91 |
8.29 |
8.56 |
7.67 |
8.00 |
8.01 |
8.28 |
2.1 |
1.2 |
1.2 |
2.00 |
2.00 |
2.00 |
17.6 |
19.8 |
17.2 |
111.0 |
110.0 |
90.0 |
|
Max. |
31.57 |
32.94 |
33.60 |
10.32 |
13.43 |
13.04 |
10.30 |
14.06 |
13.01 |
8.48 |
9.17 |
9.51 |
8.3 |
4.8 |
4.5 |
11.00 |
10.00 |
12.00 |
22.8 |
22.8 |
23.9 |
115.0 |
113.0 |
113.0 |
|
B2 |
Avg. |
30.23 |
30.71 |
30.61 |
9.31 |
10.59 |
10.40 |
9.30 |
10.61 |
10.40 |
8.15 |
8.40 |
8.89 |
4.3 |
3.4 |
2.3 |
6.53 |
3.88 |
5.28 |
20.1 |
21.2 |
20.8 |
113.0 |
111.8 |
110.7 |
Min. |
29.05 |
29.11 |
27.52 |
8.48 |
8.57 |
7.54 |
8.40 |
8.59 |
7.65 |
8.00 |
8.01 |
8.24 |
1.6 |
1.2 |
0.6 |
3.00 |
2.00 |
2.00 |
17.6 |
19.8 |
17.3 |
111.0 |
110.0 |
91.0 |
|
Max. |
31.80 |
33.77 |
33.28 |
10.69 |
14.01 |
12.77 |
10.62 |
13.77 |
12.85 |
8.50 |
9.14 |
9.51 |
8.0 |
4.9 |
4.8 |
13.00 |
9.00 |
10.00 |
22.8 |
22.8 |
23.9 |
115.0 |
113.0 |
113.0 |
|
B3 |
Avg. |
30.20 |
30.85 |
30.76 |
9.23 |
10.65 |
10.24 |
9.23 |
10.62 |
10.27 |
8.14 |
8.43 |
8.94 |
4.3 |
3.4 |
2.3 |
7.07 |
4.21 |
5.41 |
20.1 |
21.1 |
20.7 |
113.0 |
111.8 |
110.8 |
Min. |
29.01 |
29.37 |
27.49 |
8.36 |
8.67 |
7.87 |
8.21 |
8.54 |
7.77 |
8.00 |
8.00 |
8.19 |
2.0 |
1.1 |
0.7 |
3.00 |
2.00 |
2.00 |
17.6 |
19.8 |
17.5 |
111.0 |
110.0 |
104.0 |
|
Max. |
31.77 |
33.61 |
33.37 |
10.51 |
13.87 |
12.32 |
10.45 |
13.75 |
12.35 |
8.50 |
9.15 |
9.46 |
8.0 |
5.0 |
4.9 |
17.00 |
8.00 |
12.00 |
22.8 |
22.8 |
23.9 |
115.0 |
113.0 |
113.0 |
|
B4 |
Avg. |
30.19 |
30.62 |
30.55 |
9.18 |
10.48 |
10.57 |
9.15 |
10.44 |
10.52 |
8.15 |
8.43 |
8.91 |
4.3 |
3.4 |
2.5 |
7.29 |
4.52 |
5.17 |
20.1 |
21.2 |
20.7 |
113.1 |
111.9 |
111.0 |
Min. |
29.20 |
29.11 |
27.31 |
8.28 |
8.69 |
7.77 |
8.34 |
8.70 |
7.84 |
8.00 |
8.00 |
8.31 |
1.6 |
1.0 |
0.7 |
2.00 |
2.00 |
2.00 |
17.6 |
19.8 |
17.2 |
111.0 |
110.0 |
107.0 |
|
Max. |
31.76 |
33.28 |
33.40 |
10.47 |
13.46 |
12.99 |
10.30 |
13.99 |
12.89 |
8.49 |
9.16 |
9.50 |
8.2 |
4.6 |
4.8 |
17.00 |
9.00 |
12.00 |
22.8 |
22.8 |
23.9 |
115.0 |
114.0 |
114.0 |
|
C1 |
Avg. |
30.16 |
30.73 |
30.53 |
9.19 |
10.71 |
10.33 |
9.19 |
10.76 |
10.36 |
8.17 |
8.45 |
8.91 |
4.3 |
3.3 |
2.4 |
7.28 |
4.12 |
5.50 |
20.1 |
21.2 |
20.8 |
113.1 |
111.6 |
110.9 |
Min. |
29.13 |
29.12 |
27.47 |
7.99 |
8.57 |
7.55 |
8.03 |
8.58 |
7.63 |
8.00 |
8.00 |
8.13 |
2.1 |
1.3 |
1.0 |
3.00 |
2.00 |
2.00 |
17.6 |
19.8 |
17.3 |
111.0 |
110.0 |
106.0 |
|
Max. |
31.76 |
33.85 |
33.35 |
10.63 |
13.88 |
12.90 |
10.60 |
13.79 |
12.50 |
8.50 |
9.17 |
9.56 |
8.2 |
4.8 |
4.9 |
15.00 |
12.00 |
11.00 |
22.8 |
22.8 |
23.9 |
116.0 |
113.0 |
114.0 |
|
C2 |
Avg. |
30.15 |
30.62 |
30.56 |
9.24 |
10.53 |
10.35 |
9.24 |
10.54 |
10.35 |
8.13 |
8.43 |
8.92 |
4.3 |
3.3 |
2.5 |
7.88 |
4.44 |
5.55 |
20.1 |
21.2 |
20.7 |
113.1 |
111.8 |
110.9 |
Min. |
29.12 |
29.18 |
27.59 |
7.80 |
8.57 |
7.65 |
7.98 |
8.76 |
7.63 |
8.00 |
8.01 |
8.16 |
1.8 |
1.3 |
1.1 |
3.00 |
2.00 |
2.00 |
17.6 |
19.8 |
17.3 |
111.0 |
110.0 |
106.0 |
|
Max. |
31.79 |
33.87 |
33.14 |
10.45 |
13.91 |
13.03 |
10.43 |
14.01 |
13.06 |
8.50 |
9.17 |
9.43 |
8.5 |
5.1 |
4.7 |
17.00 |
9.00 |
11.00 |
22.8 |
22.8 |
23.9 |
115.0 |
113.0 |
114.0 |
|
CR1 |
Avg. |
30.20 |
30.71 |
30.58 |
9.29 |
10.63 |
10.50 |
9.29 |
10.61 |
10.44 |
8.15 |
8.43 |
8.93 |
4.3 |
3.3 |
2.3 |
7.04 |
4.08 |
5.64 |
20.1 |
21.2 |
20.7 |
113.0 |
112.0 |
110.9 |
Min. |
29.19 |
29.06 |
27.73 |
8.58 |
8.56 |
7.58 |
8.57 |
8.55 |
7.74 |
8.00 |
8.00 |
8.14 |
1.5 |
1.2 |
0.4 |
2.00 |
2.00 |
2.00 |
17.6 |
19.8 |
17.3 |
111.0 |
111.0 |
106.0 |
|
Max. |
31.57 |
33.24 |
33.07 |
10.48 |
13.94 |
13.04 |
10.57 |
13.98 |
13.04 |
8.50 |
9.17 |
9.52 |
7.9 |
4.9 |
4.8 |
11.00 |
8.00 |
12.00 |
22.8 |
22.8 |
23.9 |
115.0 |
113.0 |
114.0 |
|
CR2 |
Avg. |
30.15 |
30.61 |
30.50 |
9.22 |
10.31 |
10.15 |
9.24 |
10.40 |
10.15 |
8.15 |
8.44 |
8.91 |
4.3 |
3.3 |
2.5 |
6.52 |
4.48 |
5.92 |
20.1 |
21.1 |
20.7 |
113.0 |
111.9 |
110.8 |
Min. |
29.17 |
29.09 |
27.54 |
8.26 |
8.70 |
7.65 |
8.28 |
8.75 |
7.71 |
8.00 |
8.00 |
8.14 |
1.9 |
1.2 |
0.6 |
2.00 |
2.00 |
2.00 |
17.6 |
19.8 |
17.2 |
111.0 |
111.0 |
106.0 |
|
Max. |
31.77 |
33.86 |
33.42 |
10.34 |
13.71 |
12.33 |
10.34 |
13.44 |
12.30 |
8.49 |
9.17 |
9.51 |
7.9 |
4.8 |
4.9 |
13.00 |
12.00 |
11.00 |
22.8 |
22.8 |
23.9 |
116.0 |
113.0 |
114.0 |
|
F1 |
Avg. |
30.23 |
30.82 |
30.67 |
9.19 |
10.40 |
10.43 |
9.19 |
10.40 |
10.45 |
8.13 |
8.42 |
8.93 |
4.4 |
3.3 |
2.3 |
7.83 |
4.27 |
5.88 |
20.1 |
21.2 |
20.7 |
112.9 |
111.9 |
111.0 |
Min. |
29.05 |
29.45 |
27.63 |
8.16 |
8.59 |
7.64 |
8.33 |
8.56 |
7.61 |
8.00 |
8.00 |
8.18 |
1.6 |
1.0 |
0.7 |
3.00 |
2.00 |
2.00 |
17.6 |
19.8 |
17.4 |
111.0 |
111.0 |
107.0 |
|
Max. |
31.75 |
33.59 |
33.34 |
10.38 |
13.61 |
13.00 |
10.41 |
13.48 |
13.05 |
8.50 |
9.15 |
9.57 |
8.1 |
4.9 |
5.0 |
20.00 |
9.00 |
12.00 |
22.8 |
22.8 |
23.9 |
115.0 |
113.0 |
114.0 |
|
H1 |
Avg. |
30.19 |
30.79 |
30.57 |
9.22 |
10.61 |
10.23 |
9.23 |
10.58 |
10.23 |
8.13 |
8.42 |
8.92 |
4.3 |
3.3 |
2.3 |
7.84 |
4.40 |
5.48 |
20.1 |
21.2 |
20.7 |
113.1 |
111.8 |
110.9 |
Min. |
29.06 |
29.42 |
27.40 |
7.76 |
8.57 |
7.62 |
7.97 |
8.59 |
7.67 |
8.00 |
8.00 |
8.26 |
2.0 |
1.2 |
1.1 |
4.00 |
2.00 |
2.00 |
17.6 |
19.8 |
17.2 |
111.0 |
110.0 |
106.0 |
|
Max. |
31.77 |
33.84 |
33.43 |
10.40 |
14.07 |
13.01 |
10.28 |
13.61 |
12.80 |
8.50 |
9.17 |
9.50 |
8.2 |
4.8 |
4.9 |
16.00 |
10.00 |
12.00 |
22.8 |
22.8 |
23.9 |
115.0 |
114.0 |
114.0 |
|
M1 |
Avg. |
30.18 |
30.71 |
30.38 |
9.22 |
10.61 |
10.45 |
9.23 |
10.61 |
10.42 |
8.14 |
8.42 |
8.91 |
4.3 |
3.3 |
2.2 |
8.26 |
4.66 |
6.32 |
20.1 |
21.2 |
20.7 |
113.0 |
111.9 |
110.5 |
Min. |
29.04 |
29.42 |
27.44 |
8.08 |
8.55 |
7.60 |
8.08 |
8.60 |
7.90 |
8.00 |
8.00 |
8.13 |
2.0 |
1.0 |
1.0 |
3.00 |
2.00 |
2.00 |
17.6 |
19.8 |
17.2 |
110.0 |
110.0 |
82.0 |
|
Max. |
31.79 |
33.71 |
32.72 |
10.34 |
13.82 |
13.25 |
10.32 |
13.29 |
12.99 |
8.50 |
9.13 |
9.53 |
7.9 |
5.1 |
4.9 |
19.00 |
15.00 |
11.00 |
22.8 |
22.8 |
23.9 |
115.0 |
113.0 |
114.0 |
|
S1 |
Avg. |
30.11 |
30.56 |
30.56 |
9.16 |
10.97 |
10.97 |
9.17 |
10.94 |
10.94 |
8.15 |
8.23 |
8.23 |
4.3 |
3.1 |
3.1 |
6.85 |
4.63 |
4.63 |
20.1 |
21.6 |
21.6 |
113.0 |
111.9 |
111.9 |
Min. |
29.18 |
29.71 |
29.71 |
7.90 |
10.06 |
10.06 |
7.87 |
10.22 |
10.22 |
8.00 |
8.01 |
8.01 |
1.7 |
1.1 |
1.1 |
2.00 |
2.00 |
2.00 |
17.6 |
20.6 |
20.6 |
110.0 |
111.0 |
111.0 |
|
Max. |
31.69 |
31.79 |
31.79 |
10.24 |
11.96 |
11.96 |
10.31 |
11.65 |
11.65 |
8.48 |
8.46 |
8.46 |
8.5 |
4.0 |
4.0 |
14.00 |
10.00 |
10.00 |
22.8 |
22.7 |
22.7 |
116.0 |
113.0 |
113.0 |
|
S2 |
Avg. |
30.20 |
30.66 |
30.51 |
9.27 |
10.85 |
11.38 |
9.28 |
10.92 |
11.35 |
8.14 |
8.27 |
8.87 |
4.3 |
3.1 |
2.5 |
7.02 |
5.31 |
5.72 |
20.1 |
21.6 |
21.2 |
113.0 |
111.9 |
110.9 |
Min. |
29.06 |
29.73 |
27.57 |
7.99 |
9.88 |
9.80 |
8.09 |
10.20 |
9.64 |
8.00 |
8.03 |
8.34 |
2.1 |
1.2 |
1.4 |
2.00 |
3.00 |
3.00 |
17.6 |
20.6 |
17.2 |
111.0 |
111.0 |
106.0 |
|
Max. |
31.80 |
31.79 |
33.23 |
10.49 |
11.66 |
13.13 |
10.60 |
11.75 |
13.05 |
8.47 |
8.49 |
9.55 |
8.2 |
4.0 |
3.5 |
16.00 |
9.00 |
11.00 |
22.8 |
22.7 |
23.9 |
116.0 |
114.0 |
114.0 |
|
S3 |
Avg. |
30.14 |
30.69 |
30.61 |
9.24 |
11.05 |
11.40 |
9.24 |
11.01 |
11.40 |
8.15 |
8.24 |
8.87 |
4.3 |
3.3 |
2.3 |
7.65 |
5.43 |
6.20 |
20.1 |
21.6 |
21.2 |
112.9 |
111.8 |
111.0 |
Min. |
29.02 |
29.82 |
27.32 |
8.15 |
9.99 |
9.39 |
8.24 |
10.01 |
9.71 |
8.00 |
8.02 |
8.34 |
1.7 |
1.2 |
0.4 |
2.00 |
2.00 |
3.00 |
17.6 |
20.6 |
17.2 |
110.0 |
110.0 |
105.0 |
|
Max. |
31.78 |
31.70 |
33.36 |
10.67 |
12.14 |
13.25 |
10.63 |
12.17 |
13.18 |
8.50 |
8.50 |
9.42 |
8.5 |
3.9 |
3.8 |
18.00 |
9.00 |
11.00 |
22.8 |
22.7 |
23.9 |
115.0 |
113.0 |
114.0 |
Notes:
i. "Avg", ¡§Min¡¨ and ¡§Max¡¨ is the average, minimum and maximum respectively of the data from measurements conducted under mid-flood and mid-ebb tides at three water depths, except that of DO where the data for ¡§Surface & Middle¡¨ and ¡§Bottom¡¨ are calculated separately.
ii.
Table 2.6 Summary of Intensive DCM Impact Water Quality Monitoring Results
Locations |
Parameters |
||||||||
Salinity (ppt) |
Dissolved Oxygen (mg/L) |
pH |
Turbidity (NTU) |
Suspended Solids (mg/L) |
Temp. (oC) |
Total Alkalinity (mg/L) note ii |
|||
Surface & Middle |
Bottom |
||||||||
UC1 |
Avg. |
30.68 |
10.11 |
10.08 |
8.60 |
3.4 |
4.51 |
20.7 |
112.6 |
Min. |
29.08 |
7.56 |
7.70 |
8.01 |
1.3 |
2.00 |
17.1 |
109.0 |
|
Max. |
32.98 |
13.24 |
12.96 |
9.38 |
4.9 |
10.00 |
25.2 |
116.0 |
|
UC2 |
Avg. |
30.68 |
10.06 |
10.04 |
8.61 |
3.4 |
4.82 |
20.7 |
112.6 |
Min. |
29.13 |
7.58 |
7.67 |
8.00 |
1.3 |
2.00 |
17.1 |
109.0 |
|
Max. |
32.84 |
13.04 |
12.87 |
9.47 |
5.0 |
10.00 |
25.2 |
116.0 |
|
I1 |
Avg. |
30.66 |
10.16 |
10.19 |
8.60 |
3.4 |
4.69 |
20.7 |
112.6 |
Min. |
29.06 |
7.56 |
7.79 |
8.00 |
1.3 |
2.00 |
17.1 |
108.0 |
|
Max. |
32.91 |
13.08 |
12.92 |
9.49 |
5.0 |
10.00 |
25.2 |
117.0 |
|
I2 |
Avg. |
30.65 |
10.05 |
10.07 |
8.59 |
3.4 |
5.17 |
20.7 |
112.5 |
Min. |
29.02 |
7.64 |
7.57 |
8.00 |
1.7 |
2.00 |
17.1 |
109.0 |
|
Max. |
33.12 |
13.08 |
13.03 |
9.48 |
5.0 |
14.00 |
25.2 |
117.0 |
|
I3 |
Avg. |
30.72 |
10.03 |
10.04 |
8.60 |
3.4 |
4.95 |
20.7 |
112.5 |
Min. |
29.04 |
7.65 |
7.57 |
8.00 |
1.0 |
2.00 |
17.1 |
109.0 |
|
Max. |
32.99 |
13.30 |
13.02 |
9.46 |
4.9 |
16.00 |
25.2 |
116.0 |
|
I4 |
Avg. |
30.67 |
10.13 |
10.15 |
8.59 |
3.4 |
4.90 |
20.7 |
112.7 |
Min. |
29.07 |
7.57 |
7.96 |
8.00 |
1.8 |
2.00 |
17.1 |
109.0 |
|
Max. |
32.71 |
12.99 |
13.13 |
9.46 |
5.0 |
9.00 |
25.2 |
116.0 |
|
I5 |
Avg. |
30.72 |
10.13 |
10.12 |
8.60 |
3.4 |
5.35 |
20.7 |
112.6 |
Min. |
29.03 |
7.84 |
7.59 |
8.00 |
1.0 |
2.00 |
17.1 |
108.0 |
|
Max. |
33.07 |
13.08 |
12.80 |
9.49 |
5.1 |
14.00 |
25.2 |
116.0 |
|
I6 |
Avg. |
30.63 |
10.12 |
10.14 |
8.60 |
3.4 |
4.94 |
20.7 |
112.5 |
Min. |
29.06 |
7.55 |
7.74 |
8.00 |
1.2 |
2.00 |
17.2 |
109.0 |
|
Max. |
33.05 |
13.31 |
12.95 |
9.46 |
5.0 |
12.00 |
25.2 |
116.0 |
|
I7 |
Avg. |
30.75 |
10.10 |
10.07 |
8.59 |
3.4 |
5.19 |
20.7 |
112.5 |
Min. |
29.10 |
7.58 |
7.73 |
8.00 |
1.5 |
2.00 |
17.1 |
109.0 |
|
Max. |
33.09 |
13.01 |
12.93 |
9.48 |
4.9 |
10.00 |
25.2 |
115.0 |
|
I8 |
Avg. |
30.67 |
10.10 |
10.11 |
8.59 |
3.4 |
4.96 |
20.7 |
112.6 |
Min. |
29.06 |
7.59 |
7.76 |
8.00 |
0.9 |
2.00 |
17.2 |
109.0 |
|
Max. |
33.04 |
12.85 |
13.05 |
9.41 |
5.0 |
11.00 |
25.2 |
116.0 |
|
I9 |
Avg. |
30.65 |
10.09 |
10.10 |
8.60 |
3.4 |
5.24 |
20.7 |
112.7 |
Min. |
29.02 |
7.71 |
7.77 |
8.00 |
1.5 |
2.00 |
17.1 |
109.0 |
|
Max. |
33.00 |
12.97 |
12.86 |
9.49 |
4.9 |
16.00 |
25.2 |
116.0 |
|
I10
|
Avg. |
30.73 |
10.13 |
10.13 |
8.60 |
3.4 |
5.49 |
20.7 |
112.4 |
Min. |
29.11 |
7.65 |
7.79 |
8.00 |
1.1 |
2.00 |
17.1 |
78.0 |
|
Max. |
33.09 |
13.02 |
12.84 |
9.45 |
5.0 |
13.00 |
25.2 |
116.0 |
3. Noise Monitoring
3.1 Noise Monitoring Parameters
3.1.1 Impact noise monitoring was conducted weekly in the reporting period between 0700-1900 on normal weekdays. Additional impact noise monitoring was conducted weekly in the reporting period between 1900-0700 on all days as well as public holidays and Sundays. 3.1.2 Construction noise level measured in terms of the A-weighted equivalent continuous sound pressure level (LAeq). Leq 30min was used as the monitoring parameter for the time period between 0700 and 1900 hours on normal weekdays. Leq 5mins was used as the monitoring parameter for the time period between 1900 and 0700 as well as public holidays and Sundays. Table 3.1 summarizes the monitoring parameters, frequency and duration of the impact noise monitoring and additional impact noise monitoring.Table 3.1 Noise Monitoring Parameters, Time, Frequency and Duration
Monitoring Station |
Time |
Duration |
Parameters |
M1/ N_S1, M2/ N_S2, M3/ N_S3 |
Day time: 0700-1900 hrs (during normal weekdays) |
Once per week Leq 5min/Leq 30min (average of 6 consecutive Leq 5min) |
Leq, L10 & L90 |
M1/ N_S1, M2/ N_S2, M3/ N_S3 |
Evening time: 1900-2300 hrs (including normal weekdays, also public holidays and Sundays) |
Once per week Leq 5min (3 sets of Leq 5min) |
Leq, L10 & L90 |
M1/ N_S1, M2/ N_S2, M3/ N_S3 |
Night time: 2300-0700 hrs (including normal weekdays, also public holidays and Sundays) |
Once per week Leq 5min (3 sets of Leq 5min) |
Leq, L10 & L90 |
3.2 Noise Monitoring Locations
3.2.1 Three noise monitoring locations for impact monitoring and additional impact monitoring at the nearby sensitive receivers are shown in Figure 3.1
|
Figure 3.1 Noise monitoring locations at SKC |
Table 3.2 Noise Monitoring Location
Station |
NSR ID in EIA Report |
Noise Monitoring Location |
Type of sensitive receiver(s) |
Measurement Type |
M1 |
N_S1 |
Shek Kwu Chau Treatment & Rehabilitation Centre Hostel 1 |
Residential |
Façade |
M2 |
N_S2 |
Shek Kwu Chau Treatment & Rehabilitation Centre Hostel 2 |
Residential |
Façade |
M3 |
N_S3 |
Shek Kwu Chau Treatment & Rehabilitation Centre Hostel 3 |
Residential |
Façade |
3.3 Action and Limit Levels
3.3.1 The Action/Limit Levels in line with the criteria of Practice Note for Professional Persons (ProPECC PN 2/93) ¡§Noise from Construction Activities ¡V Non-statutory Controls¡¨ and Technical Memorandum on Environmental Impact Assessment Process issued by HKSAR Environmental Protection Department [¡§EPD¡¨] under the Environmental Impact Assessment Ordinance, Cap 499, S.16 is presented in Table 3.3.Table 3.3 Action and Limit Levels for Noise per Updated EM&A Manual
Time Period |
Action |
Limit (dB(A)) |
0700-1900 hrs on normal weekdays |
When one documented complaint is received |
75 dB(A) |
3.4 Monitoring Results and Observations
3.4.1 Impact monitoring for noise impact was conducted in the reporting period. The impact noise levels at Noise Monitoring Stations at SKC (i.e. M1/ N_S1 to M3/ N_S3) are summarized in Table 3.5. Additional impact monitoring during restricted hours was conducted in the reporting period. The additional impact noise levels at Noise Monitoring Stations at SKC (i.e. M1/ N_S1 to M3/ N_S3) are summarized in Table 3.6 and Table 3.7 respectively. Trending of the noise monitoring results is presented graphically in Appendix D. 3.4.2 Major construction activity, major noise source and extreme weather which might affect the results were recorded during the impact monitoring. 3.4.3 According to our field observations, the major noise source identified at the designated noise monitoring station in the reporting month are summarised in Table 3.4:Table 3.4 Summary of Field Observation
Monitoring Station |
Major Noise Source |
M1 |
Nil |
M2 |
Nil |
M3 |
Air-conditioning units nearby |
3.4.4 No data from impact monitoring during daytime has exceeded the stipulated limit level at 75 dB(A).
Table 3.5 Summary of Impact Noise Monitoring Results during Daytime
Location |
Noise in dB(A) |
||||||||
Range of Leq 30min |
Range of L10 5min |
Range of L90 5min |
|||||||
Jan |
Feb |
Mar |
Jan |
Feb |
Mar |
Jan |
Feb |
Mar |
|
M1 |
53.2 ¡V 51.4 |
52.6 ¡V 56.0 |
53.7 ¡V 54.9 |
51.5 ¡V 55.1 |
53.0 ¡V 59.3 |
53.7 ¡V 57.3 |
46.5 ¡V 49.5 |
53.1 ¡V 49.8 |
50.6 ¡V 54.6 |
M2 |
55.0 ¡V 55.9 |
54.6 ¡V 58.2 |
55.1 ¡V 56.5 |
56.2 ¡V 62.6 |
55.0 ¡V 63.3 |
55.4 ¡V 58.9 |
50.9 ¡V 55.7 |
50.5 ¡V 55.9 |
51.2 ¡V 55.6 |
M3 |
52.4 ¡V 53.4 |
51.8 ¡V 71.9 |
54.8 ¡V 56.0 |
53.7 ¡V 56.4 |
53.4 ¡V 82.2 |
54.6 ¡V 58.4 |
49.3 ¡V 52.4 |
48.5 ¡V 57.6 |
50.8 ¡V 54.6 |
3.4.5 Applicable mitigation measures for construction works are fully implemented as shown in Appendix B, where double-glazed windows and air conditioning system were also installed and confirmed operable for the NSRs (N_S1, N_S2 & N_S3).
3.4.6 During the noise monitoring event, frontline staffs of ET have inquired the treatment centre users on any noise disturbance from the construction activities at evening and night time, where no complaint and adverse opinions was received.
3.4.7 Data from impact monitoring during evening time and night time were compared with the NCO criteria. Where site inspection and auditing on Contractor¡¦s record have shown that the conditions stipulated in the Construction Noise Permit (CNP) issued by the Noise Control Authority for construction works during restricted hours were followed. No inappropriate practice were spotted during evening time and night time construction works, thus the stipulated requirement on noise impact control during night time and evening time was achieved.
Table 3.6 Summary of the Additional Impact Noise Monitoring Results during Evening Time
Location |
Noise in dB(A) |
||||||||
Range of Leq 5min |
Range of L10 5min |
Range of L90 5min |
|||||||
Jan |
Feb |
Mar |
Jan |
Feb |
Mar |
Jan |
Feb |
Mar |
|
M1 |
NA |
NA |
55.0 ¡V55.4 |
NA |
NA |
56.9 ¡V57.3 |
NA |
NA |
53.6 ¡V54.2 |
M2NOTE 1 |
NA |
NA |
NA |
NA |
NA |
NA |
NA |
NA |
NA |
M3 |
NA |
NA |
53.0 ¡V 54.7 |
NA |
NA |
54.8 ¡V 56.6 |
NA |
NA |
52.3 ¡V 53.3 |
Note1: An unexpected failure happened for the sound level meter on monitoring station M2.
Table 3.7 Summary of Additional Impact Noise Monitoring Results during Night Time
Location |
Noise in dB(A) |
||||||||
Range of Leq 5min |
Range of L10 5min |
Range of L90 5min |
|||||||
Jan |
Feb |
Mar |
Jan |
Feb |
Mar |
Jan |
Feb |
Mar |
|
M1 |
NA |
NA |
55.0 ¡V 55.8 |
NA |
NA |
55.3 ¡V 57.4 |
NA |
NA |
52.4 ¡V 54.8 |
M2NOTE 1 |
NA |
NA |
NA |
NA |
NA |
NA |
NA |
NA |
NA |
M3 |
NA |
NA |
53.3 ¡V 53.9 |
NA |
NA |
55.3 ¡V 55.6 |
NA |
NA |
52.4 ¡V 53.1 |
Note1: An unexpected failure happened for the sound level meter on monitoring station M2.
4.1 The waste generated from this Project includes inert construction and demolition (C&D) materials, and non-inert C&D materials. Non-inert C&D materials are made up of general refuse, vegetative wastes and recyclable wastes such as plastics and paper/cardboard packaging waste. Steel materials generated from the project are also grouped into non-inert C&D materials as the materials were not disposed of with other inert C&D materials.
4.2 As advised by the Contractor, for C&D waste, no metals were generated and collected by registered recycling collector. 0.256 tonnes of paper was generated on site and collected by registered recycling collector. No plastic waste was collected by registered recycling collector. No chemical waste was collected by licensed chemical waste collector. 6.5 m3 of other types of wastes (e.g. general refuse) were generated on site and disposed of at Landfill.
4.3 With reference to relevant handling records and trip tickets of this Project, the quantities of different types of waste generated in the reporting period are summarised in Table 4.1. Details of cumulative waste management data are presented as a waste flow table in Appendix E.
Table 4.1 Quantities of Waste Generated from the Project
Reporting Month |
Actual Quantities of Inert C&D Materials Generated Monthly |
Actual Quantities of C&D Wastes Generated Monthly |
||||||||||||
Total Quantity Generated |
Hard Rock and Large Broken Concrete (see Note 1) |
Reused in the Contract |
Reused in other Projects |
Disposed as Public Fill |
Imported Fill |
Metals |
Paper / cardboard packaging |
Plastics (see Note 2) |
Chemical Waste |
Others, e.g. general refuse (see Note 3) |
||||
Sand |
Public Fill |
Rock |
||||||||||||
(in ,000m3) |
(in ,000m3) |
(in ,000m3) |
(in ,000m3) |
(in ,000m3) |
(in ,000m3) |
(in ,000kg) |
(in ,000kg) |
(in ,000kg) |
(in ,000kg) |
(in ,000L) |
(in ,000m3) |
|||
January 2019 |
0 |
0 |
0 |
0 |
0 |
82.6139 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0.0065 |
February 2019 |
0 |
0 |
0 |
0 |
0 |
46.7821 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
March 2019 |
0 |
0 |
0 |
0 |
0 |
97.1 |
0 |
0.7552 |
0 |
0.256 |
0 |
0 |
0 |
0 |
Notes:
1. Broken concrete for recycling into aggregates.
2. Plastic refer to plastic bottles / containers, plastic sheets / foam from packaging materials.
3. Use the conversion factor: 1 full load of dumping truck being equivalent to 6.5m3 by volume.
4.4 Although there is not much waste generation in the reporting period from the Project, the Contractor is reminded to sort and store any solid and liquid waste on-site properly prior to disposal.
5.1 Coral Monitoring Parameters
5.1.1 Ten (10) tagged coral colonies at each site of suggested control site and indirect impact site are being monitored weekly for the first month and followed by monthly monitoring for three months. The selected Control Site is located at Yuen Kong Chau of Soko Islands about 7 km away from the project area. After the hitting of super typhoon Mangkhut in mid-September 2018, the coral re-tagging activities at indirect impact site and control site were conducted in November and December 2018 respectively. Tagged coral colonies at the proposed recipient site are being monitored quarterly for one year. The selected recipient site R3 is located the opposite side of the Project area at about 2 km away. 5.1.2 Monitoring recorded the following parameters (using the same methodology adopted during the pre-translocation survey); the size, presence, health conditions (percentage of mortality/bleaching) and percentage of sediment of each trans-located coral colony. The general environmental conditions including weather, sea, and tidal conditions of survey sites were monitored. 5.1.3 Health status of coral was assessed by the following criteria:Hard coral: Percentage of surface area exhibiting partial mortality and blanched/bleached area of each coral colony and degree of sedimentation.
5.2 Coral Monitoring Locations
Location of the ten tagged coral colonies at each of the proposed indirect impact site, control site, the recipient site R3 and REA transect at proposed indirect impact site are shown in Figure 5.1, Figure 5.2 and Figure 5.3 respectively:
|
Figure 5.1 Tagged Natural Corals at Indirect Impact Site Near SKC for re-tagging after typhoon Mangkhut |
|
Figure 5.2 Tagged Natural Corals at Control Site Near Yuen Kong Chau for re-tagging after typhoon Mangkhut |
|
Figure 5.3 Tagged Translocation Corals at Recipient Site R3 near SKC |
Table 5.1 Tagged Natural Corals during Baseline and Re-tagged Natural Corals after Typhoon Manghkut at Control Site near Yuen Long Chau
Coral # note i |
GPS Coordinates |
|
1 |
N22¢X09¡¦45.96¡¨ |
E113¢X54¡¦57.81¡¨ |
2R |
N22¢X11¡¦29.12¡¨ |
E113¢X59¡¦09.01¡¨ |
3 |
N22¢X09¡¦45.81¡¨ |
E113¢X54¡¦57.78¡¨ |
4 |
N22¢X09¡¦45.70¡¨ |
E113¢X54¡¦57.95¡¨ |
5R |
N22¢X11¡¦29.10¡¨ |
E113¢X59¡¦09.18¡¨ |
6 |
N22¢X09¡¦45.75¡¨ |
E113¢X54¡¦58.02¡¨ |
7R |
N22¢X11¡¦29.17¡¨ |
E113¢X59¡¦08.86¡¨ |
7 |
N22¢X09¡¦45.65¡¨ |
E113¢X54¡¦57.94¡¨ |
8 |
N22¢X09¡¦45.53¡¨ |
E113¢X54¡¦57.90¡¨ |
9 |
N22¢X09¡¦46.23¡¨ |
E113¢X54¡¦54.70¡¨ |
10R |
N22¢X11¡¦29.18¡¨ |
E113¢X59¡¦08.91¡¨ |
Notes:
i. The re-tagged corals were marked as ##R.
Table 5.2 Re-tagged Natural Corals after Typhoon Manghkut at Indirect Impact Site near SKC
Coral # note i |
GPS Coordinates |
|
11R |
N22¢X11¡¦29.14¡¨ |
E113¢X59¡¦08.92¡¨ |
12R |
N22¢X11¡¦29.12¡¨ |
E113¢X59¡¦09.01¡¨ |
13R |
N22¢X11¡¦29.11¡¨ |
E113¢X59¡¦09.07¡¨ |
14R |
N22¢X11¡¦29.13¡¨ |
E113¢X59¡¦09.12¡¨ |
15R |
N22¢X11¡¦29.10¡¨ |
E113¢X59¡¦09.18¡¨ |
16R |
N22¢X11¡¦29.07¡¨ |
E113¢X59¡¦09.23¡¨ |
17R |
N22¢X11¡¦29.17¡¨ |
E113¢X59¡¦08.86¡¨ |
18R |
N22¢X11¡¦29.14¡¨ |
E113¢X59¡¦08.94¡¨ |
19R |
N22¢X11¡¦29.20¡¨ |
E113¢X59¡¦08.81¡¨ |
20R |
N22¢X11¡¦29.18¡¨ |
E113¢X59¡¦08.91¡¨ |
Notes:
i. The re-tagged corals were marked as ##R.
Table 5.3 GPS Coordinates of Recipient Site R3
Site |
GPS Coordinates |
|
R3 |
N22¢X11¡¦43.69¡¨ |
E113¢X28.99¡¨ |
5.3 Action and Limit Levels
5.3.1 Monitoring result was reviewed and compared against the below Action Level and Limit Level (AL/LL) as set with the below Table 5.4 and Table 5.5.
Table 5.4 Action and Limit Levels for Construction Phase Coral Monitoring
Parameter |
Action Level |
Limit Level |
Mortality |
If during Impact Monitoring a 15% increase in the percentage of partial mortality on the corals occurs at more than 20% of the tagged indirect impact site coral colonies that is not recorded on the tagged corals at the control site, then the Action Level is exceeded. |
If during Impact Monitoring a 25% increase in the percentage of partial mortality on the corals occurs at more than 20% of the tagged indirect impact site coral colonies that is not recorded on the tagged corals at the control site, then the Limit Level is exceeded. |
Table 5.5 Action and Limit Levels for Post-Translocation Coral Monitoring
Parameter |
Action Level |
Limit Level |
Mortality |
If during Post-Translocation Monitoring a 15% increase in the percentage of partial mortality on the corals occurs at more than 20% of the translocated coral colonies that is not recorded on the original corals in the recipient site, then the Action Level is exceeded. |
If during Post-Translocation Monitoring a 25% increase in the percentage of partial mortality on the corals occurs at more than 20% of the translocated coral colonies that is not recorded on the original corals in the recipient site, then the Limit Level is exceeded. |
5.4 Monitoring Results and Observations
5.4.1 After the re-tagging activities were finished at both Control site and Indirect Impact site (Figure 5.1 and 5.2 respectively), the additional monthly monitoring after coral re-tagging due to the hitting of super typhoon Mangkhut in mid-September 2018 was conducted on 10 January 2019; and the weather condition was summarized in Table 5.6.
Table 5.6 Weather Condition for the Additional Monthly Post Re-Tagging Monitoring at Control Site and Indirect Impact Site
Date |
Condition |
Average Underwater Visibility |
10 January 2019 |
- Northeast force 4 to 5, - Sunny period |
Less than 0.5m |
Table 5.7 Weather Condition for the 1st Quarterly Coral Monitoring during Construction Phase at both Indirect Impact Site and Control Site
Date |
Condition |
Average Underwater Visibility |
28 March 2019 |
- Northeast force 3 - Sunny period |
Less than 0.5m |
5.4.4 Ten (10) hard coral colonies were monitored at each Control site and Indirect Impact Site as suggested in the Construction Phase Monitoring Plan. The general health conditions (size, mortality, bleaching and sediment) were recorded and summarized in Table 5.11 and Table 5.12. Photos of each coral colonies were taken during the monitoring activities shown in Appendix F. 5.4.5 The 4th Post-Translocation Monitoring was conducted on 28 March 2019 for the Recipient Site R3 (Figure 5.3) and the weather conditions were summarized in Table 5.8. Seven (7) translocated and nine (9) natural hard coral colonies were remained to monitor after the typhoon Mangkhut in mid-September 2018. The general health conditions (size, condition, mortality, bleaching and sediment) at Recipient Site were recorded and summarized in Table 5.11 and Table 5.12 respectively. Photos of each tagged corals colonies were taken and shown in Appendix F.
Table 5.8 Weather Condition for the 4th Post-Translocation Monitoring during Construction Phase at Recipient Site R3
Date |
Condition |
Average Underwater Visibility |
28 March 2019 |
- Northeast force 3 - Sunny period |
Less than 0.5m |
Table 5.9 Sizes, Condition, Mortality, Bleaching and Sediment of 10 Natural Coral Colonies at Control Site of Additional Monthly Post-Re-tagging Monitoring (10 Jan 2019) and 1st Quarterly Coral Monitoring (28 Mar 2019) during 7th to 9th Months Construction Phase Monitoring
Coral # |
Species |
Size (cm) ¡V Max. Diameter |
Condition |
Mortality (%) |
Bleaching (%) |
Sediment (%) |
||||||
Baseline (26 Jun 2018 & 3 Dec 2018) |
10 Jan 2019 |
28 Mar 2019 |
Baseline (26 Jun 2018 & 3 Dec 2018) |
10 Jan 2019 |
28 Mar 2019 |
Baseline (26 Jun 2018 & 3 Dec 2018) |
10 Jan 2019 |
28 Mar 2019 |
||||
1 |
Goniopora stutchburyi |
25 |
Fair |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
2R |
Goniopora stutchburyi |
10 |
Good |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
3 |
Psammocora superficialis |
18 |
Fair |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
4 |
Turbinaria peltata |
13 |
Good |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
5R |
Goniopora stutchburyi |
18 |
Good |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
6 |
Cyphastrea serailia |
43 |
Fair |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
7R |
Coscinaraea sp. |
15 |
Good |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
8 |
Goniopora stutchburyi |
21 |
Good |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
9 |
Goniopora stutchburyi |
11 |
Fair |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
10R |
Goniopora stutchburyi |
20 |
Good |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Notes:
i. The re-tagged corals were marked as ##R.
Table 5.10 Sizes, Condition, Mortality, Bleaching and Sediment of 10 Natural Coral Colonies at Indirect Impact Site of Additional Monthly Post-Re-tagging Monitoring (10 Jan) and 1st Quarterly Coral Monitoring (28 Mar) during 7th to 9th Months Construction Phase Monitoring
Coral # |
Species |
Size (cm) ¡V Max. Diameter |
Condition |
Mortality (%) |
Bleaching (%) |
Sediment (%) |
||||||
Baseline (23 Nov 2018) |
10 Jan 2019 |
28 Mar 2019 |
Baseline (23 Nov 2018) |
10 Jan 2019 |
28 Mar 2019 |
Baseline (23 Nov 2018) |
10 Jan 2019 |
28 Mar 2019 |
||||
11R |
Cyphastrea serailia |
48 |
Good |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
12R |
Favites chinensis |
27 |
Good |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
13R |
Turbinaria peltata |
21 |
Good |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
14R |
Favites chinensis |
8 |
Good |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
15R |
Goniopora stutchburyi |
11 |
Good |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
16R |
Psammocora superficialis |
27 |
Good |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
17R |
Favites chinensis |
15 |
Good |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
18R |
Psammocora superficialis |
39 |
Good |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
19R |
Psammocora superficialis |
42 |
Good |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
20R |
Psammocora superficialis |
29 |
Good |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Notes:
i. The re-tagged corals were marked as ##R.
Table 5.11 Sizes, Condition, Mortality, Bleaching and Sediment of 7 Translocated Coral Colonies at Recipient Site for all Post-Translocation Coral Monitoring
Coral # |
Species |
Size (cm) ¡V Max. Diameter/ Height |
Mortality (%) |
Bleaching (%) |
Sediment (%) |
||||||||||||
Baseline 23 & 24 Mar 18 |
1st 26 Jun 18 |
2nd 20 Sep 18 |
3rd 03 Dec 18 |
4th 28 Mar 19 |
Baseline 23 & 24 Mar 18 |
1st 26 Jun 18 |
2nd 20 Sep 18 |
3rd 03 Dec 18 |
4th 28 Mar 19 |
Baseline 23 & 24 Mar 18 |
1st 26 Jun 18 |
2nd 20 Sep 18 |
3rd 03 Dec 18 |
4th 28 Mar 19 |
|||
1 |
Psammocora superficialis |
35 |
0 |
0 |
15** |
15** |
15** |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
2 |
Psammocora superficialis |
N/A |
0 |
0 |
N/A |
N/A |
N/A |
0 |
0 |
N/A |
N/A |
N/A |
0 |
0 |
N/A |
N/A |
N/A |
3 |
Psammocora superficialis |
N/A |
0 |
0 |
N/A |
N/A |
N/A |
0 |
0 |
N/A |
N/A |
N/A |
0 |
0 |
N/A |
N/A |
N/A |
4 |
Turbinaria peltata |
9 |
0 |
0 |
10** |
10** |
10** |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
5 |
Goniopora stutchburyi |
N/A |
0 |
0 |
N/A |
N/A |
N/A |
0 |
0 |
N/A |
N/A |
N/A |
0 |
0 |
N/A |
N/A |
N/A |
6 |
Psammocora superficialis |
26 |
0 |
0 |
15** |
15** |
15** |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
7 |
Psammocora superficialis |
23 |
0 |
0 |
5** |
5** |
5** |
0 |
0 |
0 |
0 |
0 |
5 |
0 |
0 |
0 |
0 |
8 |
Psammocora superficialis |
N/A |
0 |
0 |
N/A |
N/A |
N/A |
0 |
0 |
N/A |
N/A |
N/A |
0 |
0 |
N/A |
N/A |
N/A |
9 |
Goniopora stutchburyi |
N/A |
0 |
0 |
N/A |
N/A |
N/A |
0 |
0 |
N/A |
N/A |
N/A |
0 |
0 |
N/A |
N/A |
N/A |
10 |
Coscinaraea n sp. |
21 |
0 |
0 |
5** |
5** |
5** |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
11 |
Psammocora superficialis |
13 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
12 |
Psammocora superficialis |
N/A |
0 |
0 |
N/A |
N/A |
N/A |
0 |
0 |
N/A |
N/A |
N/A |
0 |
0 |
N/A |
N/A |
N/A |
13 |
Psammocora superficialis |
N/A |
0 |
0 |
N/A |
N/A |
N/A |
0 |
0 |
N/A |
N/A |
N/A |
0 |
0 |
N/A |
N/A |
N/A |
14 |
Psammocora superficialis |
N/A |
0 |
0 |
N/A |
N/A |
N/A |
0 |
0 |
NA |
NA |
NA |
0 |
0 |
NA |
NA |
NA |
15 |
Goniopora stutchburyi |
N/A |
0 |
0 |
N/A |
N/A |
N/A |
0 |
0 |
N/A |
N/A |
N/A |
0 |
0 |
N/A |
N/A |
N/A |
16 |
Psammocora superficialis |
26 |
0 |
0 |
10** |
10** |
10** |
0 |
0 |
N/A |
N/A |
N/A |
0 |
0 |
N/A |
N/A |
N/A |
* N/A: Non Applicable as coral colonies were missing.
** Increased mortality was found after the hitting of super typhoon Mangkhut in Mid-September 2018.
Table 5.12 Sizes, Condition, Mortality, Bleaching and Sediment of 9 Natural Coral Colonies at Recipient Site for all Post-Translocation Coral Monitoring
Coral # |
Species |
Size (cm) ¡V Max. Diameter/ Height |
Mortality (%) |
Bleaching (%) |
Sediment (%) |
||||||||||||
Baseline 23 & 24 Mar 18 |
1st 26 Jun 18 |
2nd 20 Sep 18 |
3rd 03 Dec 18 |
4th 28 Mar 19 |
Baseline 23 & 24 Mar 18 |
1st 26 Jun 18 |
2nd 20 Sep 18 |
3rd 03 Dec 18 |
4th 28 Mar 19 |
Baseline 23 & 24 Mar 18 |
1st 26 Jun 18 |
2nd 20 Sep 18 |
3rd 03 Dec 18 |
4th 28 Mar 19 |
|||
1 |
Coscinaraea n sp. |
16 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
2 |
Psammocora superficialis |
24 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
3 |
Psammocora superficialis |
23 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
4 |
Coscinaraea n sp. |
15 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
5 |
Cyphastrea serailia |
42 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
6 |
Cyphastrea serailia |
12 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
7 |
Cyphastrea serailia |
46 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
8 |
Psammocora superficialis |
21 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
9 |
Psammocora superficialis |
19 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
10 |
Goniopora stutchburyi |
N/A |
0 |
0 |
N/A |
N/A |
N/A |
0 |
0 |
N/A |
N/A |
N/A |
0 |
0 |
N/A |
N/A |
N/A |
* N/A: Non Applicable as coral colonies were missing.
For the vessel-based marine mammal surveys, the monitoring team adopted the standard line-transect method (Buckland et al. 2001) as same as that adopted during the EIA study and pre-construction phase monitoring to allow fair comparison of marine mammal monitoring results.
Eight transect lines are set at Southeast Lantau survey area, including Shek Kwu Chau, waters between Shek Kwu Chau and the Soko Islands, inshore waters of Lantau Island (e.g. Pui O Wan) as well as southwest corner of Cheung Chau as shown in Figure 6.1 below:
|
Figure 6.1 Line Transects for Marine Mammal Surveys |
In comparison to the baseline monitoring results, results from the analyzed construction phase monitoring data would allow the detection of any changes of their usage of habitat, in response to the scheduled construction works.
6.2 Specific Mitigation Measures
6.2.1 Monitored exclusion zonesDuring the installation/re-installation/relocation process of floating type silt curtains, in order to avoid the accidental entrance and entrapment of marine mammals within the silt curtains, a monitored exclusion zone of 250 m radius from silt curtain should be implemented and monitored by competent Marine Mammal Observers (MMOs). Marine Mammal Exclusion Zone (MMEZ) would also be implemented for precautionary purpose for DCM works.
6.2.2 Marine mammal watching planUpon the completion of silt curtain installation/re-installation/relocation, marine mammal watching plan would be implemented to observe the presence of any marine mammal around the localized silt curtain or being trapped by the localized silt curtain.
6.3 Results and Observations
6.3.1 Vessel-based Line-transect Survey Six monthly surveys were conducted during the reporting period. As this is covering within the peak season (December - May) while two surveys were completed in each month during peak season. A total on effort (transects only) survey length of 246.3 km was completed, 199.5 km at Beaufort Sea State 2 or better (Table 6.1). Sixteen (16) Finless Porpoise sightings and one (1) Chinese White Dolphin sighting were recorded, twelve (12) ¡§on effort¡¨ and five (5) while transiting between transect lines (referred to as secondary line in AFCD reports; and the details of recorded sightings were summarized (Table 6.2, Figure 6.2).Table 6.1 Summary of Vessel-based Line-transect Survey Effort
Date |
Area* |
Beaufort |
Effort (km) |
Season |
Vessel |
Effort Type** |
14-01-19 |
SEL |
1 |
7.4 |
WINTER |
SMRUHK |
P |
14-01-19 |
SEL |
2 |
14.1 |
WINTER |
SMRUHK |
P |
14-01-19 |
SEL |
3 |
17.6 |
WINTER |
SMRUHK |
P |
31-01-19 |
SEL |
1 |
35.4 |
WINTER |
SMRUHK |
P |
31-01-19 |
SEL |
2 |
5.2 |
WINTER |
SMRUHK |
P |
12-02-19 |
SEL |
1 |
18.3 |
WINTER |
SMRUHK |
P |
12-02-19 |
SEL |
2 |
14.8 |
WINTER |
SMRUHK |
P |
12-02-19 |
SEL |
3 |
8.1 |
WINTER |
SMRUHK |
P |
26-02-19 |
SEL |
1 |
6.6 |
WINTER |
SMRUHK |
P |
26-02-19 |
SEL |
2 |
18.5 |
WINTER |
SMRUHK |
P |
26-02-19 |
SEL |
3 |
16.4 |
WINTER |
SMRUHK |
P |
18-03-19 |
SEL |
1 |
9.0 |
SPRING |
SMRUHK |
P |
18-03-19 |
SEL |
2 |
29.2 |
SPRING |
SMRUHK |
P |
18-03-19 |
SEL |
3 |
4.2 |
SPRING |
SMRUHK |
P |
28-03-19 |
SEL |
1 |
41.5 |
SPRING |
SMRUHK |
P |
* As shown in Figure. 6.1
** P (from AFCD) denotes the ON EFFORT survey on the transect line, not the adjoining passages
Table 6.2 Summary of Sightings Recorded during January 2019 to March 2019 of Vessel-based Line-transect Survey Effort
Date |
Species |
Sighting No. |
Group Size |
PSD |
Behaviour |
Latitude |
Longitude |
Area |
Effort Type |
Season |
14-01-19 |
Finless Porpoise |
7 |
1 |
N/A |
Unknown |
22.1757 |
113.948 |
SEL |
OFF |
WINTER |
31-01-19 |
Finless Porpoise |
8 |
2 |
N/A |
Travel |
22.1635 |
113.9521 |
SEL |
OFF |
WINTER |
31-01-19 |
Finless Porpoise |
9 |
1 |
79 |
Travel |
22.1726 |
113.9736 |
SEL |
ON |
WINTER |
31-01-19 |
Chinese White Dolphin |
10 |
2 |
139 |
Feeding |
22.2197 |
113.9748 |
SEL |
ON |
WINTER |
31-01-19 |
Finless Porpoise |
11 |
2 |
0 |
Travel |
22.1774 |
113.9933 |
SEL |
ON |
WINTER |
31-01-19 |
Finless Porpoise |
12 |
1 |
0 |
Unknown |
22.1917 |
114.0126 |
SEL |
ON |
WINTER |
12-02-19 |
Finless Porpoise |
13 |
3 |
22 |
Travel |
22.1882 |
113.9535 |
SEL |
ON |
WINTER |
12-02-19 |
Finless Porpoise |
14 |
2 |
N/A |
Travel |
22.2002 |
113.9782 |
SEL |
OFF |
WINTER |
12-02-19 |
Finless Porpoise |
15 |
3 |
20 |
Unknown |
22.2173 |
113.9543 |
SEL |
ON |
WINTER |
26-02-19 |
Finless Porpoise |
16 |
4 |
N/A |
Travel |
22.2021 |
113.9831 |
SEL |
OFF |
WINTER |
26-02-19 |
Finless Porpoise |
17 |
2 |
N/A |
Travel |
22.1910 |
113.9758 |
SEL |
OFF |
WINTER |
18-03-19 |
Finless Porpoise |
18 |
1 |
20 |
Travelling |
22.21253 |
113.9837 |
SEL |
ON |
SPRING |
28-03-19 |
Finless Porpoise |
19 |
4 |
33 |
Travelling |
22.18111 |
113.9451 |
SEL |
ON |
SPRING |
28-03-19 |
Finless Porpoise |
20 |
3 |
27 |
Travelling |
22.17312 |
113.9452 |
SEL |
ON |
SPRING |
28-03-19 |
Finless Porpoise |
21 |
2 |
126 |
Travelling |
22.17532 |
113.9542 |
SEL |
ON |
SPRING |
28-03-19 |
Finless Porpoise |
22 |
1 |
121 |
Travelling |
22.18774 |
113.9623 |
SEL |
ON |
SPRING |
28-03-19 |
Finless Porpoise |
23 |
2 |
20 |
Feeding |
22.17603 |
113.9837 |
SEL |
ON |
SPRING |
Figure 6.2 Location of sightings recorded during January to March 2019 Vessel-based Line-transect Survey
Figure 6.3 Plot of encounter rate during January to March in 2009 ¡V 2019 from different surveys
A review of the long term AFCD marine mammal monitoring programme, the EIA and the pre-construction baseline monitoring report for this project was conducted. Both the EIA and the pre-construction baseline monitoring were conducted during the peak porpoise months (Dec 2008 to May 2009 and Feb-April 2018, respectively. The AFCD long term monitoring data, the EIA and baseline information could be compared directly to Impact Survey results of the reporting period. A review of the Beaufort Sea state survey conditions between 2009 and 2018 (only data available from AFCD at time of writing; (AFCD 2018; 2017; 2016; 2015; 2014; 2013; 2012; 2011; 2010)) shows that survey conditions in January to March 2019 were within the % limits of previous AFCD surveys, and much better than surveys conducted during the EIA. A review of all the porpoise sightings in the survey area for January to March between 2009-2018 indicates that there are fluctuations between the number of sightings usually recorded in January to March. Given the similar survey conditions and the encounter rate recorded for porpoise in the project area during the reporting period, the encounter rate for January to March 2019 were 0.06km-1, 0.06km-1 and 0.07km-1 respectively (see Figure 6.3), it is noted that the encounter rate of impact survey lied at the approximate a half of the baseline survey for February survey. It highlighted the inherent variability for surveys that focused on relatively small populations of highly mobile individuals. When comparing on March survey results, the encounter rate in March 2019 impact survey was approximately the same as the March 2018 baseline survey. Such extremely low encounter rates during the reporting period in a small part of the finless porpoise habitat, significant differences in sightings might be impossible to calculate. It is difficult to draw conclusions with regards to impacts on marine mammals as predicted in the EIA and the effectiveness of project mitigation measures during the initial phase of construction activities. As surveys continue for this project, data shall be constantly re-evaluated across survey months to discern trends and impacts, if any. 6.3.2 Specific Mitigation Measures Silt curtains were deployed for sand blanket laying works and DCM trial during the reporting period. At least two MMO were on duty for continuous monitoring of the Marine Mammal Exclusion Zone (MMEZ) for DCM trial works and installation/re-installation/relocation process of silt curtains, and the marine mammal trapping checking and silt curtains inspection in accordance with the Detailed Monitoring Programme of Finless Porpoise and Marine Mammal Watching Plan respectively. Trainings for the MMO were provided by the ET prior to the aforementioned works, with a cumulative total of 63 individuals being trained and the training records kept by the ET. From the Marine Mammal Watching observation records and MMEZ monitoring log records, no Finless Porpoise or other marine mammals were observed within or around the MMEZ and silt curtains in the reporting month. 6.3.3 PAM and Land-based Theodolite TrackingThese tracking surveys will be conducted during the peak season between December 2018 and May 2019 for 30 surveys during the peak season to provide good temporal coverage during the initial stage of the construction period.
Theodolite surveys were conducted on 21/02, 22/02, 28/02, 01/03, 04/03, 05/03, 06/03, 12/03, 13/03, 15/03, 20/03, 21/03, 22/03, 26/03, 27/03 and 29/03. Five to six hours of monitoring were conducted each day. As anticipated, site barges obstructed much of the immediate view. Theodolite data shall be analysed at the end of the survey period, as per the format and analyses procedures presented in the baseline report for this project.
6.3.4 Photo records of the marine mammal monitoring taken during the reporting period are presented in Appendix G.
7.1 WBSE Monitoring Parameters
7.1.1 Information to be collected included feeding, perching/roosting, preening, soaring, flying, nesting and territorial guarding and the time spent on each activity. The responses and reactions to any disturbance to the WBSEs were also recorded and examined in conjunction with the construction noise and/or other events in the vicinity. Other disturbances such as weather condition, or invasion by other fauna species were also recorded.7.2.1 Six monitoring for monthly construction phase were conducted during the reporting period. Since there is no landing point along the western part of SKC, boat survey was used for the monitoring survey. In order to increase the chance of finding the WBSEs, monitoring survey was carried out either early in the morning or later in the afternoon. The weather conditions of monitoring survey were shown in Table 7.1.
Table 7.1 Weather Conditions during the WBSE Monitoring (Monthly)
Date |
Condition |
Temperature (¢J) |
9 January 2019 |
- Northeast 5 to 6 - Sunny |
23 |
30 January 2019 |
- Northeast force 3 to 4 - Sunny |
25 |
16 February 2019 |
- Northeast 3 to 4 - Sunny |
26 |
27 February 2019 |
- North 4 to 5 - Sunny |
25 |
20 March 2019 |
- East force 3 to 4 - Sunny |
25 |
31 March 2019 |
- Southeast force 4 to 5 - Sunny |
27 |
Table 7.2 Weather Conditions during the WBSE Monitoring (7 consecutive daily)
Date |
Condition |
Temperature (¢J) |
21 March 2019 |
- Southeast force 3 to 4 - Sunny |
22 |
22 March 2019 |
- Southeast force 4 to 5 - Sunny |
24 |
23 March 2019 |
- Southeast force 4 to 5 - Sunny |
26 |
24 March 2019 |
- East force 4 to 5 - Sunny |
23 |
25 March 2019 |
- East force 4 to 5 - Sunny |
24 |
26 March 2019 |
- Southeast force 3 to 4 - Sunny |
25 |
27 March 2019 |
- Southeast force 3 - Sunny |
28 |
Figure 7.1 Location of WBSE Nest on SKC
7.2.5 No invasion of other fauna species was recorded and no sign of using the construction site as a foraging ground was recorded as well. 7.2.6 During the reporting period, no abnormal behaviour of the recorded adults was shown. All marine works during the seventh to ninth months construction period did not show any influence to the WBSE. 7.2.7 Photo records of the WBSE taken during the reporting period are presented in Appendix H.
8.1 No exceedance of the Action and Limit Levels of the regular construction noise, coral and WBSE monitoring was recorded during the reporting period.
8.2 For general & regular DCM water monitoring, thirty-nine (39) & twenty-four (24) of the water quality monitoring results for Suspended Solid (SS) obtained during the reporting period had exceeded the relevant Action and Limit Levels respectively. Thirteen (13) & twenty (20) of the water quality monitoring results for SS reported during January 2019, four (4) & one (1) of the water quality monitoring results for SS reported during February 2019 and twenty-two (22) & three (3) of the water quality monitoring results for SS reported during March 2019. For initial intensive DCM water monitoring, thirty (30) & ninety (90) of the water quality monitoring results for Suspended Solid (SS) obtained during the reporting period had exceeded the relevant Action and Limit Levels respectively. Twenty-four (24) & sixty-two (62) of the water quality monitoring results for SS reported during February 2019 and six (6) and twenty-eight (28) of the water quality monitoring results for SS reported during March 2019.
8.3 Findings from investigations carried out immediately for each of the exceedance cases during the reporting period had showed that these exceedances were unrelated to the Project, however, environmental deficiencies of the Contractor on the implementation of silt curtain deployment system were spotted.
8.4 Further investigation was made with the Contractor on the silt curtain design and checking procedure as stated in the deposited Silt Curtain Deployment Plan. Rectification actions regarding to the improper implementation of silt curtain system shall be carried out immediately.
8.5 The Contractor has been reminded that all measures recommended in the deposited Silt Curtain Deployment Plan shall be fully and properly implemented for the Project as per Clause 2.6A of the FEP.
8.6 The Contractor has been reminded to facilitate the ET¡¦s investigation in the time frame stated at Event and Action plan under the updated EM&A Manual by promptly providing site records and information.
8.7 No notification of summons and prosecution was received in the reporting period.
8.8 Statistics on complaints, notifications of summons and successful prosecutions are summarized in Appendix I.
9. EM&A Site Inspection
9.1 Site inspections were carried out on a weekly basis to monitor the implementation of proper environmental pollution control and mitigation measures under the Contract. Site inspections were carried out at the Site Portions 1, 1A & 1B and Portion 7 during the reporting period. Portions 1, 1A & 1B were the sites near SKC within the Site boundary and Portion 7 was the site at Tung Chung for stockpiling of construction materials.
9.2 Joint site inspection with IEC was carried out on a monthly basis.
9.3 Minor deficiencies were observed during weekly site inspection. Key observations during the site inspections are summarized below:
¡P Site tidiness were not maintained properly
¡P Prevention actions for oil/chemical spillage were not carried out properly
¡P Silt curtains were not deployed properly
¡P Damage of deployed silt curtains was found
¡P Sand was accumulated on the pontoon¡¦s surface
9.4 The Contractor has rectified most of the observations identified during environmental site inspections in the reporting period.
9.5 During site inspection, installed silt curtain were found damaged for some idling works. The contractor was reminded to properly fix and maintain the deployed silt curtains prior to the operation of concerned construction works during the site walk by ET and IEC. The Contractor conducted the maintenance of deployed silt curtain immediately before resuming any construction works.
9.6 According to the EIA Study Report, Environmental Permit, contract documents and Updated EM&A Manual, the mitigation measures detailed in the documents, except the silt curtain system, are implemented as much as practical during the reporting period. An updated Implementation Status of Environmental Mitigation Measures (EMIS) is provided in Appendix B.
10. Conclusion and Recommendations
10.1 This 3rd Quarterly Environmental Monitoring and Audit (EM&A) Report summarizes the EM&A works undertaken during the period from 1 January 2019 to 31 March 2019 in accordance with the Updated EM&A Manual and the requirement under EP- 429/2012/A and FEP-01/429/2012/A.
10.2 Construction noise, water quality, construction waste, coral, marine mammal and White-Bellied Sea Eagle (WBSE) monitoring were carried out in the reporting period. No project-related exceedance of the Action and Limit Level was recorded during the reporting period, however, environmental deficiencies of the Contractor on the implementation of silt curtain deployment system were spotted.
10.3 Weekly environmental site inspection was conducted during the reporting period. Environmental deficiencies were observed during site inspection and were rectified.
10.4 The Contractor has been reminded to facilitate the ET¡¦s investigation in the time frame stated at Event and Action plan under the updated EM&A Manual by promptly providing site records and information.
10.5 According to the environmental site inspections performed in the reporting period, the Contractor is reminded to pay attention on maintaining site tidiness and avoidance of oil spillage on-site and sand accumulation on the pontoon surface during sand blanket laying works.
10.6 Regarding to the deployment of silt curtains as a principal water quality impact mitigation measures on various marine works, the Contractor has been reminded to follow strictly to the design and checking procedure as specified in the Silt Curtain Deployment Plan. As the scale of DCM works will be stepped up in the coming months, the Contractor has been reminded to pay extra attention on the status of deployed silt curtain. The Contractor is reminded that all measures recommended in the deposited silt curtain deployment plan shall be fully and properly implemented for the Project as per EP condition 2.6 of the FEP.
10.7 As the dredging works was conducted in the reporting period, the Contractor had been reminded to follow strictly to the design and checking procedure as specified in the Silt Curtain Deployment Plan for the dredging works. The Contractor had been reminded to follow the regulation on rate and means for dredging works as stipulated in FEP Clause 2.17 ¡V 2.21. The Contractor is reminded to follow Dumping At Sea Ordinance (DASO) for the storage, handling and disposal of dredged materials.
10.8 No environmental complaint was received in the reporting period.
10.9 No notification of summons or prosecution was received since commencement of the Contract.
10.10 The ET will keep track on the construction works to confirm compliance of environmental requirements and the proper implementation of all necessary mitigation measures.